PROJECT MANAGEMENT
RED ZUMA PROJECT
SUBMITTED BY:-
TASK ID 1 – MARKET ANALYSIS 2 – PRODUCT DESIGN 3 – MANUFACTURING STUDY 4 – PRODUCT DESIGN SELECTION 5 – DETAILED MARKETING PLAN 6 – MANUFACTURING PROCESS 7 – DETAILED PRODUCT DESIGN 8 – BUILD PROTOTYPES 9 – LAB TEST PROTOTYPE 10 – FIELD TEST PROTOTYPE 11 – FINALIZED PRODUCT DESIGN 12 – FINAL MANUFACTURING PROCESS 13 – ORDER COMPONENTS 14 – ORDER PRODUCTION EQUIPMENT 15 – INSTALL PRODUCTION EQUIPMENT 16 – CELEBRATE
NETWORK SCHEDULE
5
2 1
4
6
3 7
12
9
14 15
11 8 10
13
16
TASK ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
DURATION 25 30 20 10 15 30 45 25 10 15 20 10 7 14 35 1
ES 0 25 25 55 65 65 65 110 135 135 150 170 170 180 224 259
LS 0 25 15 55 244 120 65 110 140 135 150 170 204 194 224 259
EF 25 55 45 65 80 95 110 135 145 150 170 180 177 194 259 260
LF 25 55 55 65 259 150 110 135 150 150 170 180 204 194 259 260
The project is estimated to be completed in 260 days The critical path for the project is 1 – 2 – 4 – 7 – 8 – 10 – 11 – 12 – 14 – 15 – 16 Activity 5 i.e detailed marketing plan has highest amount of slack (179)
SLACK 0 0 10 0 179 55 0 0 5 0 0 0 27 0 0 0