3
Issue for approval
15/02/2017
Yeu Wee Chek
Mohd. Asri
Lim Seong San
2
Issue for approval
21/12/2016
Yeu Wee Chek
Mohd. Asri
Lim Seong San
1
Issue for approval
09/05/2016
Yeu Wee Chek
Norshairazi
Lim Seong San
0
Issue for approval
17/03/2016
Yeu Wee Chek
Norshairazi
Lim Seong San
Planning Engineer
WSHO
Project Manager
Prepared
Checked
Approved
Designation Rev
Description
Date
CLIENT
PUBLIC UTILITIES BOARD
CONSULTANT
CH2M HILL SINGAPORE PTE LTD
SUB CONTRACTORS
MAIN-CONTRACTOR
HSL CONSTRUCTOR PTE LTD PROJECT TITLE
Improvement to Bedok Canal Contract 1 (Between East Coast Parkway and the Sea) PROJECT DOCUMENT / DRAWING TITLE
METHOD STATEMENT & RISK ASSESSMENT OF SHEET PILING WORKS
PROJECT DOCUMENT / DRAWING NO.
10-0115P025-MS-015
REVISION NO. 3
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
2of 24
Contents 1.
INTRODUCTION .............................................................................................................................. 3
2.
SCOPE ............................................................................................................................................. 3
3.
PURPOSE ........................................................................................................................................ 3
4.
REFERENCE DOCUMETNS ........................................................................................................... 3
5.
LIST OF EQUIPMENT / MACHINERIES ......................................................................................... 3
6.
PROCEDURES FOR SITE COMPOUND SET UP .......................................................................... 4 6.1
PERMIT ............................................................................................................................... 4
6.2
DAILY TOOL BOX MEETING............................................................................................. 4
6.3
PRE-START INVESTIGATION & SURVEY ....................................................................... 4
6.4
LOCATION OF SITE ........................................................................................................... 4
6.5
SCOPE OF WORK .............................................................................................................. 5
6.6
ORGANISATION CHART ................................................................................................... 5
6.7
SITE PROCEDURES & METHODOLOGY ......................................................................... 6
6.8
INSTALLATION METHOD OF SHEET PILING ................................................................. 6 6.8.1 HOISTING OF SHEET PILES .................................................................................... 7 6.8.2 NORMAL SILENT PILING METHOD ......................................................................... 7 6.8.3 SILENT PILING WITH WATER JETTING METHOD ............................................... 10 6.8.4 VIBRATORY EXCAVATOR METHOD ..................................................................... 11 6.8.5 VIBRATORY HAMMER METHOD ........................................................................... 11 6.8.6 EXTRACTION OF SHEET PILES ............................................................................ 12
6.9
FABRICATION OF SHEET PILES ON SITE .................................................................... 13 6.9.1 SHEET PILES TING FABRICATION ............................................................... 13 6.9.2 CORNER PILE FABRICATION ................................................................................ 14 6.9.3 TAPERED PILE FABRICATION .............................................................................. 14
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
3of 24
1. INTRODUCTION The statement is submitted here for the purpose of better understanding to the client as to how the different elements of the project will be executed through disciplined approach by HSL Constructor Pte Ltd. It will act as a communication among various parties and personnel involved in the project, giving an idea of the methods, procedures, safety measures and prudent techniques that will be adopted for successful completion of the works. Serving as a working document, the method statement shall identify the responsibilities of the contractor and its staff and also ensure that quality of works meet the standard specification. HSL Constructor Pte Ltd has been awarded to work on the Improvement to Bedok Canal Contract 1 for upgrading and widening existing canal structures. Our client is Public Utilities Board of Singapore. 2. SCOPE This work will be carried out to enlarge existing Bedok canal from 46.7m into 60m width. There are various stages of construction. In the first phase of widening canal, contractor is required to construct a temporary flow diversion to deal with intense storms from upstream during construction. Earth Retaining Steel Structures (ERSS) will be installed to form the flow diversion canal in approximately length 310m and width 42m. After completion of temporary canal construction, the existing canal will be sealed off for construction activity. Marine cofferdam cells will then be constructed at the southern side of canal.
3. PURPOSE The purpose of this method statement is to outline procedures and methodology for installation of sheet piles by adopting silent piling methods.
4. REFERENCE DOCUMETNS A. B. C. D. E. F. G. H.
Working Procedures of Normal ‘Press In Method’ Working Procedures of Normal ‘Water Jetting Method’ Sheet Piling Plan (subjected to revision in length) Silent Piler Machine Model ECO100 Catalogue Silent Piler Machine Model SA100 Catalogue Silent Piler Machine Model SA150 Catalogue Lifting Plan Mill Certificates & Factory Production Certificates
5. LIST OF EQUIPMENT / MACHINERIES A. Surveying Total Stations
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
B. C. D. E.
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
4of 24
Theodolites Silent Piler Machines Welding Consumables Crawler Crane (80 tons)
6. PROCEDURES FOR SITE COMPOUND SET UP 6.1 PERMIT
All works will only be allowed to commence upon approval of the permit-to-work by HSL. 6.2 DAILY TOOL BOX MEETING
Daily toolbox meeting shall be conducted prior daily commencement of work, briefing and highlighting on all job scopes and hazards involved to all site personnel.
6.3 PRE-START INVESTIGATION & SURVEY
Prior to commencement of site works, an external survey will be carried out to confirm existing area over sheet piling locations and the condition of existing environment. A photographic record will be taken during dismantling, which will be maintained as construction record. 6.4 LOCATION OF SITE
The project site is located at the eastern part of Singapore, East Coast Parkway and the Sea.
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
5of 24
6.5 SCOPE OF WORK
The scope of work for constructing temporary flow diversion canal as planned in stage 1 of flow diversion scheme is summarized as follows: a. Setting out and location markings b. Installation of sheet pilings and construction of marine cofferdam cells c. Completion sheet piling works and cofferdam cells
6.6 ORGANISATION CHART
The tentative work schedule for works in this MS as follows:
HSL CONSTRUCTOR PTE LTD
CONSTRUCTION MANAGER Tan Soo Peng (M: 8481 0763)
To oversee all works relating to the construction site.
WSH COORDINATOR Muhammad Hairizam (M: 9711 6390) To monitor and advise all HSR matters relating to the construction site.
SUPERVISOR Selvam Prabu (M: 9174 6606)
SUPERVISOR Low Chiew Siang (M: 8257 6441)
To supervise all works in SITE are in accordance to specifications and to ensure a safe, healthy and environment friendly work area
To supervise all works in workshop are in accordance to specifications and to ensure a safe, healthy and environment friendly work area
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
6of 24
6.7 SITE PROCEDURES & METHODOLOGY
Prior to the beginning of work, contractor shall locate the position of work by establishing and marking the sheet pilings. The sheet pilings, part of ERSS structures shall be constructed in accordance with the details on the plans and all work shall be performed in a workmanlike manner satisfactory to Professional Engineer. Follow up the completion of sheet piling insertions, ground monitoring devices will be installed to monitor and control major ground movement in the vicinity of site. Ground monitoring devices shall be installed and calibrated properly before starting of excavation activity. a. Site Inspection / Preparation Site inspection, site clearance, cable detection and utility diversion/ protection to be carried out along sheet pile alignment according to all available information. Trial trenches to be carried out by main contractor to confirm the location of the existing services prior to the driving of sheet piles. b. Safety Measures Before the start of installation work, metal hoarding and safety nets shall be erected and installed around the vacant land where it is to be carried out by main contractor, if necessary. c. Certificate All operators, welders shall carry relevant certificates/licenses during the work. Likewise, all lifting operation related certifications shall be submitted prior to work commencement. d. Signboards All installation works will be carried out within the hoarded working compound area, therefore sign boards for traffic control and pedestrian are needed to install by main contractor, if necessary. Working area shall be barricaded by main contractor if the operation is in the public area. For night operation, warning lights shall be arranged by main contractor. e. Setting out Setting out of sheet pile to be conducted by main contractor surveyor, to set out internal wall of the sheet piles and the position of each pile and to establish TBMs on site for determining the cut-off levels of sheet piles. 6.8 INSTALLATION METHOD OF SHEET PILING
This working activity will be carried out by our appointed sub-contractor, Kian Hock. Conventionally, sheet piles have been vibrated or pounded into the ground. However, such method inevitably generates excess noise and vibration that could affect the stability of structures in site vicinity. Therefore, silent pilers will be introduced to utilise press-in force (the setting criteria of pile is set as maximum 800 kN or to the designed length, whichever come first) and hydraulically jack in piles into ground. Generally, normal ‘Press In Method’ will be applied. Wherever there
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
10-0115P025-MS-015
Rev. No.
3
Date
15/02/2017
Page
7of 24
is encountering of difficult soil conditions, auxiliary ‘Water Jetting Method’ will be introduced to enable piles to be pressed into. In addition, water jetting method can be utilized as means to significantly improve productivity and cost, as well as optimizing the sheet pile section required.
6.8.1 HOISTING OF SHEET PILES
Hoisting of Sheet piles for installation by Crawler crane. a. Lifting crane shall be selected, based on the weight of the to be lifted. Crawler crane shall be certified by PE according to the Factory Act of Singapore. b. Working access and area shall be good and wide enough for this type of work including swing operation. c. Lifting supervisor shall be assigned for the operation. Riggers, signalman and etc. shall be well organized. They shall be instructed clearly for the operation. d. Crawler crane shall park at the pre-determined positions. Sheet piles lay down area shall be selected at the early stage. e. Ensure the shackle has a valid LG certificate (issued by AE/PE) before used. f.
The maximum hoisting capacity for shackle is 8 tons.
g. Handle it carefully & slot into the pre-cut center hole diameter 50mm at the top of sheet piles. (100mm from the top of sheet piles) h. Push the shackle into pre-cut center hole (referred to item g). i.
Rigger man will ensure the shackle fully tightens.
j.
The whole lifting operations should be supervised by lifting supervisor.
k. Once the sheet pile has inserted to the silent piler chuck by crane and press in at least 3/4 length of sheet piles into the ground, silent piler operator will confirm and ensure everything is in order before giving instruction to the trigger man to release the shackle. The shackle must be reachable by a man height. l.
Repeat it again for next installation & extraction of sheet pile or H-beam.
6.8.2 NORMAL SILENT PILING METHOD
The sheet piling is started from a reaction stand which simulates the top of sheet piles. After positioning the reaction stand vertically on proposed alignment, the initial 3-4 pieces of sheet
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
8of 24
piles shall be pitched and pressed-in using the silent piler machine to the required depth. Counterweights, often in the form of sheet piles are used to provide an initial reaction force. Upon completion installation of initial 3-4 pieces, the counterweights and reaction stand shall be removed. Then, installation for the remaining sheet piles shall continue.
The next sheet pile shall be pitched into the chuck of the silent piler machine. After checking the verticality and alignment, the sheet pile shall be pressed-in to the required depth. If necessary, sheet pile shall be ed by welding to achieve the required penetration length. However, prior to completing the driving of sheet pile, the silent piler machine is released from the anchoring piles. Then, the main body of silent piler machine is lifted and travelled forward. The main body is lowered and the feet are clamped on the next three piles. The silent piler machine shall complete the driving of the sheet pile and upper portion of the machine move forward to allow the next sheet pile to be pitched. The above procedures shall be repeated to press-in the subsequent sheet piles to complete the sheet pile wall.
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
9of 24
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
10of 24
6.8.3 SILENT PILING WITH WATER JETTING METHOD
This method executes the driving work as follows: A water-conveyance pipe (water supply hose) with a nozzle attached at the tip is welded to the U-shaped section of driving steel sheet pile with a pipe band. The jet water supplied from a water jet pump is injected through the nozzle to reduce the driving resistance, driving the steel sheet pile into the soil. After the pile is correctly driven into the soil, the water jet is shut off, and the jet pipe is extracted from the soil to apply for the next steel sheet pile. This method is designed to feed the water supplied in a water tank into the water jet pump, which, in turn, pressurizes and feeds the water through the water supply hose and pipe line for injection from the nozzle.
On the other hand, the water jet tly method is intended to facilitate smooth, accurate, and damage-free driving of steel sheet piles by reducing point resistance, skin friction resistance, and t friction resistance caused by driving operation with the aid of water jet from the water jet pump. Injection of water jet into sandy soil can cause pore water pressure in soil particles to temporarily increase, leading to easily moving soil particles and resultant so-called 'liquefaction.' This phenomenon is used to reduce the point resistance of steel sheet pile. In addition, excess water may flow along the side of steel sheet pile out to the surface, helping reduce the skin friction resistance. Furthermore, washing of sand from the ts of already driven steel sheet piles causes eliminated 'wedge phenomenon' of ts, leading to reduced t friction resistance. When the injection is interrupted after completion of pile driving, the water propagates through the soil to produce so-called water-binding phenomenon, contributing to more consolidated soils than before. This phenomenon helps stabilize the already driven steel sheet piles, and produce proper reaction forces allowing driving of subsequent steel sheet
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
11of 24
piles. Sometimes it is reported that 'use of the water jet tly method for driving of steel sheet piles can cause loosened soils in the surrounding ground and resultant caved-in road surfaces and/or damaged houses, and thus the water jet tly method is never adopted.' In practice, however, proper control of water flow and pressure helps produce the waterbinding phenomenon in the site soils after completion of driving, and the soils become consolidated, having little effect on the surrounding sites. This suggests that safe, secure, and environment-friendly methods should be selected for driving of steel sheet piles, and the water jet tly method is the most reliable among the currently available methods.
6.8.4 VIBRATORY EXCAVATOR METHOD
Due to unpredictable soil condition on site, contractor may face difficulties in using silent piler method. It could be vary soil profiles at certain locations which impose higher resistance to driving stresses and thus limit the usage of silent piler method. For such circumstance, vibro-mounted excavator is advisably used to tackle the hard soil condition problems. The vibrodrivers are specifically designed to be mounted directly on the stick of excavators. Vibro-mounted excavator are efficient hydraulic vibratory hammers that reduce the cohesion of soil through vibration, and allowing to easily drive in sheet pile. Despite of the advantages, excavators in the current market has limited boom length. Hence this method is only suitable for installation of sheet pile with length less than 14m. Sheet piles will be lay down at reachable distance of vibro-mounted excavator. Then, driver will clamp to the end of sheet pile. It will be pitched up and vibrated in place, until the required toe level is reached. Contractors shall ensure that vibration limits are not exceeded during sheet pile extraction by using vibration method. 6.8.5 VIBRATORY HAMMER METHOD
Due to limitation of vibro-mounted excavator, vibratory hammer would be used to tackle hard ground condition and installation of sheet pile length more than 14m. As of common procedure, sheet piles will be transported and off-load on site at working locations.
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
10-0115P025-MS-015
Rev. No.
3
Date
15/02/2017
Page
12of 24
Temporary frame guide beam will be fixed at survey lines in order to ensure verticality and alignment of sheet piles. The guide frame will consist of vertical end (legs) along with two I-beams will be fixed horizontally, with a gap provided between their faces in order to allow for the pitching of the sheet piles. Then, vibratory hammer’s clutches will pitch the sheet pile and lift it up by crawler crane. The sheet piles will be attached a safe line with feature of release shackle attachment. Then, it will be pitched down by the vibration force of hammer. During the operation, contractor has to be careful and to ensure that vibration limits are not exceeded. 6.8.6 EXTRACTION OF SHEET PILES Silent Method
The sheet pile extraction using silent piler method is a unique self-moving technique which enables the machine (silent piler) to extract along the sheet piles which were driven earlier. The silent piler machine is lifted by a service crane/excavator to “sit in” the existing sheet piles. The main body is lowered and the feet are clamped on the sheet piles. The sheet piles extraction operation in then commenced. This extraction operation is the reverse on the installation operation. After the chuck of the silent piler machine had gripped on first sheet pile, the sheet pile is pulled vertically upwards. If necessary, sheet pile shall be cut to facilitate the extraction works. However, prior to completing the extraction of sheet pile, the silent piler machine is released from the anchoring piles. Then, the main body of silent piler machine is lifted and travelled backwards. The main body is lowered and the feet are clamped on the next three piles. The silent piler machine shall complete the extracting of the first sheet pile. The upper portion of the machine move backwards to allow the next sheet pile to be extracted. The above procedures shall be repeated to extract the subsequent sheet piles to complete the sheet pile extraction work.
Vibration Method Sheet piles tend to be easy to be extracted by vibration method. After backfilling or completion of permanent structure, vibratory hammer will be brought in together with crawler crane. Crane will lift the vibratory hammer to work locations and clamp the sheet pile. Once power is generated, vibration force induced from hammer will reduce cohesion of soil and start to pull out sheet piles. At the same time, crawler crane will gently adjust its boom radius to pull up sheet piles. The same operation will be repeated until each sheet pile is lifted up. Contractors shall ensure that vibration limits are not exceeded during sheet pile extraction by using vibration method. All extracted sheet piles and materials, will be loaded and transport off-site.
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
13of 24
Secondary line must be strictly enforced while using excavator vibro method
6.9 FABRICATION OF SHEET PILES ON SITE
Most of the 21m sheet piles will be ing on site due to transport difficulty for 21m length (normal lorry truck can only fit maximum 18m length). Asides of that, total 15 numbers of corner piles will be pre-fabricated prior to installation. They are especially needed for sharp turning points in ERSS at seaside. Due to nature of work, tapered pile will also be fabricated and installed at every 200th sheet pile. The purpose of tapered pile is to adjust and ensure the vertical alignment of sheet piles. 6.9.1 SHEET PILES TING FABRICATION
2 pieces of sheet piles will be selected, lifted and placed at designated location for ting in welds. After placing, lifting gears will be detached. Welders start to prepare and grind one of the edge of sheet piles until it become bevel edge. After that, both ends of sheet piles (one end with normal edge, another end with bevel edge) to be put together, merged and ted as per welding details stated below.
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
14of 24
Sheet pile will be left for cooling down of 3 hours before lifting. Then, lifting team will rig the sheet pile properly and flip over it. After that, welding will be carried out at another side of sheet pile t. 6.9.2 CORNER PILE FABRICATION
Corner pile is a special sheet pile to create T-section and form an interlocking element to connect sheet piles so that they can be combined with special corner profiles. Before the start of work, 2 nos. of sheet piles in length 21m will be selected and laid properly at fabrication yard. Firstly, sheet pile will be cut into half and left for cooling down about few hours. Angle bars with size of 100x100x12mm will be welded onto another sheet pile at interval of 3.5m. Welding details of angle bar with sheet pile can be referred to attachment F: Sheet Pile Fabrication Detail. Then, the half-cut sheet pile is lifted and slotted into pre-t angle bars spacing. The sheet pile alignment will be adjusted so that it is in right position. Afterwards, welders will start to weld and t angle bars and sheet pile. Finally, fabricated sheet piles will be shifted to another storage location waiting for installation.
6.9.3 TAPERED PILE FABRICATION
If at any time the sheet pile wall vertical alignment is tilted and out of line of connection slot, contractor will provide tapered pile to insure succeeding piles are vertical. 2 nos. of sheet piles will be selected and laid properly at fabrication yard. The first step of cutting sequence, sheet pile will be cut along its diagonal line. After it left for cooling down for 3 hours, it will be lifted and put adjacent to another sheet pile. Next, it will be adjusted and confirmed in position before another t welding begins. Welder will start to weld the t at both sides as per details in attachment F: Sheet Pile Fabrication Detail. After
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
15of 24
that, splice plates will be welded to strengthen connection of sheet piles. Finally, the fabricated sheet piles will be shifted to another storage location for installation. Investigation should be carried out to review the cause and ensure there is no ‘de-clutching’ of sheet piles.
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
16of 24
APPENDIX A ATTACHMENT: LOCATION LAYOUT PLAN
sheet of
2
12
1. GENERAL: BUILDING AND CONSTRUCTION CONTRACTOR SHALL CHECK ALL THE DIMENSIONS SLOPES OR ANGLES AND DETAILS IN STRUCTURAL DRAWING. IF DISCREPANCIES OCCURS, HE SHALL INFORM THE ENGINEER BEFORE FABRICATION OF STEEL FRAMEWORK.
AUTHORITY APPROVED UNDER SECTION 5/SECTION 5A OF THE BUILDING CONTROL ACT (CAP 29)
2. FABRICATION:
Project Ref No: E3440-00010-2014-ST100
FABRICATION OF STEEL FRAMEWORK SHALL FULLY COMPLY WITH BRITISH STANDARD AND CODE OF PRACTICE, WHERE APPLICABLE.
3. ERECTION:
20 16 33
80 8
CONSIDERATION SHALL BE PAID TO THE STABILITY AND SAFETY OF STEEL FRAMEWORK DURING ERECTION SEQUENCE.
4. STRUCTURAL STEEL: 77 T1 62 T1 78 T1
3P 67 05 27 MK
60 T1
54 13
59 T1
63 13
Y
61 13 7 52 16 13
56 14
58 T1
1F 42 LP 38 14
55 14
36 14
3 T6 4 T6
T
S
A
S
A
O
1 T6
2 T6
T
37 14
C
1L 87 09 27 MK
K
R
A
P
E
A
W
68 13
8F 42 LP
5 T6
6 T6
56 11
0 T6
33 13
A
7 T6
9 34 LP
9 T5 35 11
36 11
9F 41 LP 32 13
84 T1
N AI DR
39 11 40 11
O
C
96 16
95 16 94 16
90 16 92 16 91 16
56 13
57 13
55 13
60 13
48 13
21 10
20 T5
94 11
96 11
95 11 93 11 91 112 9 11 89 10 19 11
20 10
98 11
19 10
18 11
58 12
B B
82 11
P G 77 Q/ BB
33 T4
30 T4 B
15 T6
39 T4
81 11
34 T4
30 / H1 P
50P / G3
19 14
54 14
EB
71 14
22 14
45 14
17 14
33 14
69 14
TH
94 13
77 12 97 13
78 12
87 12 98 13
97 11
EN OP
N AI DR
88 11
19 12
32 4 21 2 13 13 12
18 T6
4D T6
17 T6
27 T6
37 T6
E 41 T6
A 41 T6
45 T6 46 T6
0 64 41 T T6
36 T6
Description
Rev Date
32 T6
89 T6
ABH 6
84 T6
83 T6
77 T6
34 T6
81 T6
66 T6 50 T6
61 T6
53 T6 51 T6
52 T6
63 T6
60 T6 58 T6
65 T6
87 T6
85 T6
43 T5
ABH 10
78 79 T6 T6 80 T6
86 T6
MAIN CONTRACTOR:
90 T6
91 T6
88 T6
E ) 05 3 + CH ( 92 T6
ABH 7
76 T6
93 T6
94 T6
42 T7
75 T6
74 T6 82 T6 73 T6 72 T6
70 T6
42D Penjuru Road Singapore 609162
67 T6
Tel: +65 6898 5225
Fax: +65 6898 5156
64 T6
59 T6 62 T6
55 T6
96 T6
95 T6
33 T6
35 T6
39 T6
43 T6 42 T6 44 T6
91 23 44 11
76 11
77 11
EN OP
30 T6 28 T6 31 T6
29 T6
38 T6
47 T6
95 12
71 11
69 11 70 11
2 117
58 13
3m 0.
01 T7
26 T6
25 T6 23 T6
B C 41 641 T T6
48 T6
49 T6
98 T3
P 19 / G4
00 T7
21 T7
20 T6
20 P G4/
N AI DR
03 T7
02 T7
19 T7
97 T6
22 T6
19 T6
29 43 12 12
30 12 42 21 13 12
74 11
EN OP
04 T7
18 T7
20 T7
98 T6
89 12
75 11
3m 0.
23 T7
24 T6
21 T6
71 T6
B
25 T7
24 T7
69 T6
B
26 T7
42 T7
68 T6
B
22 T7
29 T7
24 12
20 12
49 12
P
05 T7
07 T7
30 14 32 14
22 1221 12
97 812 129
96 12
90 12
85 11
86 11
63 12
22 / G4 21 / PG4
B 02 T4
23 12
01 12
87 11
62 21 16 12
64 12
67 12 68 29 16 12
91 12 92 12
81 79 12 0 12 8 12 84 11
65 12
95 11
94 11
96 11
03 12
66 12
34 20 4 15 2 13 12
82 12 83 12 89 81 11 11
82 11 83 11
00 12
47 12
45 12
46 08 12 12
A 02 T4
96 T3
m 25 0.
06 T7
17 T7
99 T6
NE LI
33 14
PA
96 13
99 11
48 12
02 12
PE PI m N 25 AI . DR
OF RO
08 T7
A 10 T7
16 T7
28 T7
30 T7
VE
T
98 11
76 12
09 12
Ø
95 T3
02 T4
09 T7
10 T7
15 T7
27 T7
R SE RE
O
1 41 1 4 1 14
12 14
4 20 14 4 12
36 29 7 13 3 22 11
30 3/ PG
14 T7
43 T7
) ng Lo
FO
95 13
13 14
70 14
43 14
EN OP m 25 0. N AI DR
D ) 6 2 2 H C (
11 T7
GE NA AI
72 14
UNDER ST100 (THIS) SUBMISSION
13 T7
31 T7
DR
EB
44 14
80 14
99 31T3 / G3 P
21 14
18 14
34 14
00 T4
P 32 / G3
0X 87 09 27 MK
34 14
9 47 1 8 7 7 7 4 4 1 1
46 14
4 47 15 6 77 44 11
01 T4
39 T7
32 T7
NE LI
39 12
55 14
P
33 / G3
m 21 V( I PFS
38 12
73 14
03 T4
12 T7
ABH 5
VE
35 14
04 T4 P 34 / G3
41 T7
33 T7
R SE RE
49 / G3
40 T7
36 T7
GE NA AI
38 T4
Date
37 T7
35 T7
DR
37 12
37 T4
06 APR.2016
Date
31 / PH1
) ng Lo
31 27 11 11
77 11
78 11
36 12
P
35 T4
35 / G3
P
06 APR.2016
32 P / H1
42 T5
55 11
56 27 1 11
16 T6
2 7 1 92 1 12 11 11
79 11
36 T4
N I XDRA DEBO m WI 9 . 0
54 11
0 23 17 11 1
07 T4
05 T4
45 77 11 21 11 11
48P / G3
80 11
P 36 / G3
E I NG APOR
39 T5
M 21 V( I PFS
10 12
06 T4
02 10
09 28 10 12
P
01 10
83 14 18 11
60 12
47 P / G3
P G 78 Q/ BB
37 / G3
00 10
85 16 18 11
55 56 12 12 54 12
32 T4
33 P / H1
43 T5
8 101
57 12
59 12
28 T4
3875 S
E I NG APOR
) 26 2 CH ( 38 T7
13 T6
14 T6
4367 S
38 T5
40 T5
29 / H1
) 78 C 1 + ABH 11 CH (
WU RUIXIN
39 T7
41 T5
L 90 T4
26 11
61 12
31 T4
29 T4
35 P H1/
35 T5
36 T5
87 11
62 12
05 12
6 70 1 02 12
A 07 T4
38 / G3
26 T5
25 T5
34 / H1 P
44 T5
28 / H1 P
40 T4
G 80 Q/ P BB
P
34 T5
46 T5
88 11
99 11
4 20 1 03 12
B 07 T4
45 T5
B
00 12
G 79 Q/ BB
ABH 4
47 T5
37 T5
P 46 / G3
D
36P / H1
33 T5
42 T4
P
10 T4
82 T5
27 / H1 P
01 2 2 1 0 12
09 T4
19 T5
27 T5
49 T5
J 90 T4
27 T4
DR LI GUOJUN
18 T5
23 T5
28 T5
32 T5
81 T5
P
CIVIL
29 T5
30 T5
12 T6
18 T4
08 T4
39 / G3
17 T5
22 T5
31 T5
25 T4
P
GEOTECHNICAL
L E A ON N SI G S
R EE IN
0X 87 09 27 MK
79 T5 80 T5
26 / H1
19 T4
R EE IN
30 T5
21 T5
I 90 T4
11 T6
L E A ON N SI G S
16 T5
46 13
46 T4
Qualified Person Endorsement :
47 13
27 11
78 T5
83 T5 25 P H1/
10 T6
45 P / G3
Date
61 13
22 10
86 T5
43 T4
26 T4
06 APR.2016
Date
49 13
23 10
17 11
75 T5
K 90 T4
21 T4
06 APR.2016
N
15 T5
52 T5
53 T5
44 / G3
20 T4
57 T5
55 T5
51 T5
77 T5 87 T5
H 90 T4
ABH 12
BUILDING CONTROL ACT SINGAPORE
50 13
L
) ng Lo
76 T5
24 P H1/
48 T4
41 T4
3K 98 08 27 MK
72 T5
56 T5
24 T4
17 T4
C 8) 17 + CH (
48 T5
12 T4
N AI
A
84 T5
49 T4
13 T4
14 T4 11 T4
P 40 / G3
13 T5
54 T5
16 T4
15 T4
59 T5
14 T5
47 T4
BUILDING CONTROL ACT SINGAPORE
12 T5
60 T5
71 T5
73 T5
P
42 / G3
41 PG3/
DR
N
NE LI
70 T5
22 T4
23 T4
EN OP
A
VE 74 T5
G 90 T4
97 11
P
5m 37 0.
C
R SE RE 23 / H1 P 09 T6 50 T4
44 T4
43 / G3
59 13
K
67 T5
45 T4
P
51 13
O
0X 87 09 27 MK
P
GE NA AI
38 14
N
73 13
D
90 T5
89 T5
69 T5
) B 0 3 1 + CH (
AL RE ON TI NT NA CE NG LI I SA
52 13
78 13
80 13
79 13
81 13
E
97 T5
DR
55 18
56 18
57 18
3K 98 08 27 MK
72 13
97 13
98 13
82 13
24 10
B 0X 87 -09 27 MK
98 T5
61 T5
85 T5
Registration No. A029
11 T5
99 T5
In AC Organization
LAU WEI HING
10 T5
58 T5
E 90 T4
CHAN EWE JIN
09 T5
ABH 3
88 T5
20 15
58 / G3 P
NO: 1152
02 14
96 13
83 13
91 T5
92 T5
28 11
m 14 V( I PFS
54 18
36 20 35 20
19 15
59 / G3 P
D 08 T5
64 T5
63 T5
22 / H1
08 T6
3K 98 08 27 MK
NO: 7033
54 3 13 135
77 13
99 13
84 13
93 T5
68 T5
51 T4
75 13
95 13
94 T5
F 90 T4
ABH 13
74 T2 60 / G3 P 73 T2
74 13
76 13
94 13
32 55 11 11
16 11
52 18
53 18
61 / G3 P
00 14
85 13
NE LI
66 T5
P
52 T4
01 14
93 13
86 13
VE
00 T6
07 T6
62P / G3
72 T2
89 16
93 16
87 16
92 13
39 13
R SE RE
C 08 T5
65 T5
21 / H1
N AI DR
54 T4
3m 0.
68 T2
87 13
GE NA AI
51 18
24 20
X BO
76 T2
70 T2
97 16
91 13
DR
85 19
DE WI
) 30 1 + CH (
3 / P H1
4 / H1 P
06 T6
N
1) THE EXCAVATION SITE SHALL BE ENCLOSEDBEFORE ANY EXCAVATION WORK TO BE CARRY OUT. 2) ALL SLOPE SHALL BE COVERED BY 50MM LEAN CONCRETE OR EQUIVALENCE ONCE THE SOIL IS EXPOSED. 3) THE FINAL SET AND TERMINATION OF THE KING POST SHALL BE JACKED / DRIVED UNTIL REFUSAL. 4) THE SHEET PILE IN 14M LONG SHALL BE DRIVED TO SET.
1 / H1
B 08 T5
95 T5
96 T5
FS PI V( 21m Lon g)
55 T4
98 T2
69 T2
ABH 2
5P / H1
01 T6
D 90 T4
3K 98 08 27 MK
B P
P 2 / H1
20 / H1 P
53 T4
71 T2
58 13
88 13
29 11
57 T4
9m 0.
01 T3
96 T2
94 T2
38 13
C 90 T4
05 T6
58 T4
07 T5
08 T5
69 16
25 10
ABH 14
16 19
92 T2
95 T2
90 13
15 11
66 / G3 P
64 / G3 P
10 T3
N I A R D
95 T4
6P / H1
06 T5
FS PI V( 14m Lon g)
96 T4
60 T4
63 / G3 P
N E P O
98 16
26 10
48 18
02 T6
P 19 / H1
18 T3
05 T5
A 08 T5
45 T7
44 T7
56 T4
85 T2
93 T2
H
03 T6 04 T6 61 T4
11 T3
99 T2
75 T2
T
18 / H1
21 19
17 19 18 19
91 10
09 T3
97 T2
80 T2
A
02 T3
88 T2
91 T2
75 14
80 16
41 13
30 11
04 18
7 / H1 P P
65 / G3 P
84 T2
98 T4 97 T4
O
59 T4
08 T3 86 T2
84 14
94 4 7 4 1 18
95 17
03 18
N E P O
ACCREDITED CHECKER
7. EXCAVATION AND PILING:
03 T5
T
N I A R D
07 T3
89 T2
82 T2
86 16
85 16 84 16
37 13
73 17
47 18
3m 0.
03 T3
00 T5
99 T4
O
04 11
83 T2
N AI
Y AR
74 17
71 17 45 18 46 18
15 19
04 T3
N O PE 3m N 0. AI DR
ND
96 17
99 17
05 18
90 T2
EB
F
62 T4
SPECIALIST ACCREDITED CHECKER
01 T5
50 18
44 20
17 T3
81 16
U BO
42 13
36 13
76 17
98 17
75 17
8 / H1 P
67 T4
01 18 02 18
00 18
21 T3
16 T3
12 T3
87 T2
DR
63 15
43 13
77 17
78 17
2 78 13 8 17 84 17
72 17
06 18
19 T3
06 T3
04 T5
B 90 T4
65 T4
07 18
49 18
14 19
67 / G3
Accredited Checker Endorsement :
ANCHOR BOLT SHALL BE AS BS 4419 (CAST-IN) STEEL BAR WITH YIELD STRENGTH OF 250N/mm2.
02 T5
17 / H1 P
63 T4
6. ANCHOR BOLT:
6P 63 09 27 MK
T LO
27 10
10 12
13 12
79 17
93 T4
66 T4
) A 45 + CH (
P
00 T3
EB
15 12
31 11
35 13
2 9 23 11
81 17
80 17
97 17
09 19
10 19
3K 98 08 27 MK
ABH 15
94 T4
90 18
05 T3
4 T2
EB
44 13
11 12
16 12
40 12
34 12
B
0X 87 09 27 MK
P
15 T3
9 33 LP
62 15
45 13
38 12
35 12
85 17
ABH 1
37 14 12 11
36 12
86 17
28 12908 1
07 19
DE I W N m AI 65 0. DR X BO
64 T4
13 19
6 T2
5 T2
EN OP
55 15
83 16
82 16
46 13
34 13
9 / H1
P 6 1 / H1
12 19
62 17
EB
61 17
EB
68 / G3 P
22 T3
N AI DR
60 17
EB
W
EN OP
59 17
B B E E
6m 0.
13 T3
DE I
5 204
6 T9
14 T3
0 34 LP
7 T2
EB
33 13
53 12
68 T4
AL RE ON TI ENT NA C NG LI I SA
11 19
26 T3
23 T3
8 T2 EB
79 14
85 14
3m 0.
51 13
47 13
32 13
54 12
P
B 12 12
24 12
29 12
70 17
DE I W RT 9m LVE 0. CU X BO
25 T3
EN OP 3m N 0. AI DR
20 T3
41 19
T
63 17
4 T9
EB
52 13
52 15
50 13
49 13
48 13
55 12
31 12
30 12
DE I mW 6 . 0 N RAI ND OPE
69 T4
68 17
O
66 17
S
S
D
69 / G3 P
64 17
A
E
T
65 17
1 T3
A
A
O
E
C
24 T3
67 17
46 20
13 11
2 T3
K
R
A
P 1 34 LP
V
R
I
69 17
E
S 5 T3 4 T3 3 T3
C
EB
53 15
29 13
30 13
29 10
19 17
10 11 11 11
47 20
R
7 T3
6 T3
6F 41 LP
EB
86 14
74 14
70 14
10 16
11 16
31 13
18 17
28 10
22 10
2N 37 07 27 MK
92 T4
0 T4
2 34 LP
0 T3
N
90 T4
15 P 1/ H
3 T4
4 T8
8 T8
EB
87 T4
03 16
56 12
19 11122 1
20 11 59 14 21 11
91 T4
3 34 LP
9 T3
5 T9
54 13 55 11
71 14
50 15
46 15
69 14
09 17
60 14
61 14
14317 1111 21 1
13 18 11 11
4F 34
5 T4
4 T4
2 T4
8 T3
9 T2
82 T4
84 T4
88 T4
1) WELDING PROCEDURE SHALL CONFORM TO BS 5136:74 2) ALL WELDING ELECTRODES SHALL BE COMPLY WITH BS 639. 3) WELDING OPERATION SHALL CONFORM WITH BS 449(1959), BS 639(1976) AND OTHER BS CODES WHERE APPLICABLE. 4) ALL WELDING SHOULD BE DONE IN APPROVED MANNER TO PREVENT ANY DISTORTION. DISTORTION GREATER THAN 6mm IN 3000mm WILL BE REJECTED AND SHOULD NOT BE ACCUMULATIVE. 5) ALL FILLET WELD EXPOSED TO WEATHER SHALL NOT BE LESS THAN 8mm UNLESS OTHERWISE STATED. 6) ALL CONNECTIONS TO BE WELDED UNLESS OTHERWISE SHOWN.
80 T4
81 T4
3 T8
1 T4
9 T8
LP
N AI DR
2 T8
8F 41 LP
T
5 T8
4F 41 LP
33 15 6 1 15
1 18 53 1 15
9 10 53 15 1
0 9 2 2 5 5 1 1
28 21 15 15
68 14
67 14
66 14
049 51 111
65 1464 14
63 1462 14
95 01 11 11 16 11
19 10
EN OP DE WI
A ) 45 + CH ( 10P / H1
20 10
0 T8
2m 1.
1 T8
6 T8
2 T9
A 86 T4
83 T4
A 90 T4
B
70 T4 6 T4
K
7 T8
3 T9
77 T4
T ER LV CU
89 T4
11 P / H1
14 / H1 P
21 10
A
O
C S
R
A
T
S
7 T4
9 T7
48 20
P
8 T7
Y
A
W
1 T9
5. WELDING:
85 T4
BMBH5 71 T4
DE I W 6m 0. EN OP I N A DR
07 6 11 108 110 1 05 11
0F 42 LP 49 20
42 T1
EB
76 T4
86 T4
P 12 / H1
50 20
7 T7
0 T9
79 T4
EN OP m N 35 AI 0. DR
78 T4
0 . D 3m R A OP I N E N
N I DRA
DE I W N AI 6m 0. DR EN OP
B
3P 67 05 27 MK
E
DE I W N AI 6m 0. DR EN OP
DE I W N AI 6m 0. DR EN OP
DE I W RT 6m LVE 0. CU PE PI
27 15 22 15
90 13 51 20
13 / H1 P
T
A
74 T4
47 15
23 13
26 13
S
A
72 T4
T
S
A
O
73 T4
91 13
25 13
3F 41 LP 45 T1
75 T4
E
K
5F 34 LP
Y
K
R
A
T
S
A
E
C
T
24 13
A
W
E
N AI DR
2F 42 LP
47 T1
43 T1
EN OP
S
A
O
37 13 38 13
50 T1 49 T1
C
C
pe Pi
5F 41 LP
48 T1
44 T1
6 34 LP 8 T4
I
V
2 37 51 15 1
53 T1
R
A
P
9 T4
R
E
S
0 T5
4F 42 LP
0 00 . 0 + CH
54 T1
N AI DR
1L 87 09 27 MK
D
73 14 72 14
EN OP DE WI
3m 0.
P
1 T5
56 T1
O
R
7 34 LP
A
92 13
5 T7
52 T1
46 T1
4 T5
3 T5
2 T5
6 T7 55 T1
92 T1
W
4 T7
7F 41 LP
51 T1
2m 1.
3 T7
N AI DR
57 T1
90 T1
8 34 LP
EB
5 T5
EN OP DE I
27 11
28 11
2m . 1
6 T5
1 T7
2 T7
T
S
A
E
7 T5 EB
6F 42 LP
54 3 1 55 11
88 T1 89 T1
91 T1
A
30 13
8 T5
9 T6 0 T7
K
T
S
43 13
26 11
R
A
P
93 13
42 13
EN OP
33 14
55 11
54 11
87 T1
37 11 38 11
7C 01 08 27 MK
3m 0.
35 14
31 13
85 T1
8 T6
Y
A
W
82 T1
83 T1
86 T1
00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 ) 00 ng 60 00 Lo 60 m 00 14 60 V( 00 I 60 P00 FS 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60 00 60
57 14
EB
35 14
1) ALL SHEET PILE, STEEL WALER, STEEL STRUT AND KINGPOST USED SHOULD BE IN GOOD CONDITION. 2) ALL STEEL SECTION AND PLATE SHALL CONFORM TO BC1, CERTIFIED MATERIAL STEEL GRADE FROM APPENDIX A OF BC1. 3) ALL STEEL SHALL BE SOUND AND FREE FROM CRACKS, SURFACE FLAWS, LAMINATION AND OTHER DEFECTS, SHEET PILE SHOULD HAVE A GOOD INTERLOCKING TO ACHIEVE WATER TIGHT. RTO SHOULD CHECK THOROUGHLY ALL THE AND OBTAIN ERSS PE APPROVAL BEFORE INSTALLATION ON SITE. 4) ALL STRUCTURAL STEEL USED TO BE GRADE S355. EXCEPT OTHERS SPECIFIED.
61 T1
81 T1
PRO FE
80 T1
PRO FE
58 14
79 T1
Consultant :
57 T6
N AI DR
25 11 28 14
4 136
3 136 62 13
18 P 4/ G
24 11
WRX ENGINEERS Pte.Ltd.
97 T3 P 1 76 Q/ BB 76 Q/ P BB
(CIVIL & STRUCTURAL ENGINEERING CONSULTANTS) 27 14
93 T3
ERSS LAYOUT PLAN (OVERALL)
190 Middle Road, #18-05, Fortune Centre
SCALE 1:1000
86 T3
Singapore 188979 Tel 62727071 Fax 62787071
P
LEGENDS:
ABH 9 13 10
80 90 01 11
91 T3
87 T3
14 10
92 T3
90 T3
85 T3
03 11
84 T3
Email :
[email protected]
15 10
75 Q/ BB
0X 87 09 27 MK
89 T3
- ADDITIONAL BOREHOLE (ABH)
7 9 90 01 01 11 11
1 107
- EXISTING BOREHOLE (BH)
m 21 V( I P FS
) ng Lo
CATCHMENT AND WATERWAYS DEPARTMENT
B
02 116 0 11
BH
) 05 E 3 ABH 8 + CH (
12 10
ABH
11 10
88 T3
BMBH1
Project Title :
IMPROVEMENT OF BEDOK CANAL BETWEEN EAST COAST PARKWAY AND THE SEA ON LOT05673P PT, LOT09870X PT, MK 27, AT EAST COAST PARKWAY
BMBH2
Drawing Title :
ERSS LAYOUT PLAN (OVERALL)
DESIGNED :
DRAWN :
CHECKED : RM
AY
JOB NO :
SCALE :
15016
AS SHOWN
WRX
DATE : 23 OCT. 2015
DRAWING NO. :
15016/CWD/BDK/ERSS/FP1-1
REV.
-
THE OWNERSHIP OF THE COPYRIGHT IN THIS DRAWING IS RETAINED BY WRX ENGINEERS WHOSE WRITTEN CONSENT MUST FIRST BE OBTAINED BEFORE ANY USE OR REPRODUCTION OF THE DRAWING OR ANY PART THEREOF TO BE MADE.
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
17of 24
APPENDIX B ATTACHMENT: CONSTRUCTION DRAWING
sheet of
12
N
4
BUILDING AND CONSTRUCTION 1689
AUTHORITY 1690 1695
1691
APPROVED UNDER SECTION 5/SECTION 5A OF THE BUILDING CONTROL ACT (CAP 29)
1692 1694
1693 1696
1356
1355
1354 1353
1352
1351
1350
1359
1349
1697 1360
1348
1698
1361
1479 1347 1346 1475
Project Ref No: E3440-00010-2014-ST100 1514
1357
1486 1515
1485
1484
1687
1474
80 8
1435
EB
EB
1516
FSP-IV (14m Long)
1433
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
1473 1472
CB r
DETAIL '1'
C B r
TYPE 1
1686
10665
6000
20 16 33
1517
1358
1603
B R
Cbr
KP
B R
KP
11 89 4
1709
KP
1254
1150 1149
Pi pe
1465 1464
1324 1325
11 95 2
KP
KP B R
1323
1326
Cbr
KP
1718
1461
1460
1107 1106 1108 1105
1459 1120 1118
11 91 2
1719
1113 1121
1119 1122 1109 1115 1116
1114 1123 1117
1337 1338
KP
KP
RB
RB KP
KP
10226
RB KP
KP CB r
10762
KP
42000
10231
LST
CB r
RB
CB r
RB
RB KP
KP
10226
CB r
CB r
CB r
KP
KP
CB r
RB
RB
CB r
CBr
RB
Accredited Checker Endorsement :
SL ACCREDITED CHECKER DRAI NAGERESERVEL I NE
NO: 1152
3700 3700 3700 3700 3700 3700
CHAN EWE JIN In AC Organization Registration No. A029
FSP-IV (21m Long)
BUILDING CONTROL ACT SINGAPORE
Cbr
11 95 3
1463 1462
KP
KP
KP
RB
RB KP
KP
B R
Cbr
Cbr 1669
RB
KP
KP
1255
1256
KP
B R
B R
1253
KP
RB KP
KP
Cbr
DRAI NAGERESERVEL I NE
1466
KP
37 40 37 00 37 00 37 00 37 00 37 S 00 L 37 00 37 00 37 00 37 00 37 00 24 70
B R
KP
RB
RB
CBr
60 00
KP
RB
RB
KP
KP
r CB
B R
Cbr
TH
RB RB
KP
KP
RB
RB KP
r CB
PA
KP
r CB
T
RB
r CB
FO
O
Cbr
1467
B R
r CB
1522
KP
B R
KP
CB r
RB RB KP
1468
KP
CB r
CBr CBr
KP B R
KP
KP
KP
RB
RB
RB
RB
RB
CB r
60 00
B R
60 00
1521
RB
CBr
1680
TYPE 1
CB r
CBr CBr
S L
1681
KP
r CB
KP
1682
1611
RB
RB
r CB
60 00
KP RB
KP B R
KP
KP
r CB
1610
KP B R
r CB
1520
B R
RB
RB KP
r CB
1683
RB
RB KP
r CB
DETAIL '1'
1469
KP
r CB
1546
1519
RB
KP
RB
r CB
1547
KP
r CB
FS PI V 60 (1 00 4m
1550
1518
r CB
EASTCOASTPARK WAY
1563
60 00
Lo ng )
EB
1562 1555
60 00
EB EB
CBr
60 00
1552
r CB
1553
r CB
1471
1470
SL r CB
1685 1684
r CB
r CB
60 00
RB
06 APR.2016 Date
Qualified Person Endorsement :
L E A ON N SI G S
CIVIL
R EE IN
PRO FE
B
WU RUIXIN
BEDOK CANAL
3875 S
E I NG APOR
06 APR.2016 Date
1071
1153 1152 1155
1231
1216 1211
1212
DRAI NAGERESERVEL I NE
DRAI NAGERESERVEL I NE
1110 1111
1210
1154
1215
1213
1117
1119
1118
1116
1115
1114
1236
1235
1234 1177
Description
Rev Date 1178 1230 1780
1779
1224
1179 1778
MAIN CONTRACTOR:
1777
1797
UNDER ST100 (THIS) SUBMISSION
1229
1907
1228 1908 1776
1180
1181
1798
42D Penjuru Road Singapore 609162 Tel: +65 6898 5225
SHEET PILING AND STRUTTING LAYOUT PLAN FOR PHASE 1 SCALE 1:500
1500
1000
1500
Fax: +65 6898 5156
Consultant :
SHEET PILE FSP-IV
WRX ENGINEERS Pte.Ltd.
STEEL MEMBER SCHEDULE
(CIVIL & STRUCTURAL ENGINEERING CONSULTANTS) 190 Middle Road, #18-05, Fortune Centre
SIZE
SL
WALER FOR LACED STRUT
UC 400x400x147 Kg/m
S355
L-ST
LACED STRUT
2UC 300x300x94 Kg/m
S355
CATCHMENT AND WATERWAYS
S-ST
SINGLE STRUT
UB 350x350x137 Kg/m
S275
DEPARTMENT
KP
KINGPOST
UC 300x300x94 Kg/m
S275
RS
RAKER STRUT
UB 400x400x197 Kg/m
S355
WS
WALER FOR RAKER STRUT
UB 400x400x283 Kg/m
S355
RB
RUNNER BEAM
UB 300x300x106 Kg/m
S275
SL (WALER)
1500
LAU WEI HING BUILDING CONTROL ACT SINGAPORE
CROSS BRACING
UB 150x150x31 Kg/m
Project Title :
IMPROVEMENT OF BEDOK CANAL BETWEEN EAST COAST PARKWAY AND THE SEA ON
06 APR.2016 CBr
Email :
[email protected]
NO: 7033
LST
STEEL GRADE
Singapore 188979 Tel 62727071 Fax 62787071
TYPE
SPECIALIST ACCREDITED CHECKER
S275
LOT05673P PT, LOT09870X PT, MK 27, AT
Date
EAST COAST PARKWAY
NOTE: FOR CONNECTION DETAIL, REFER TO DRAWING NO. 15016/CWD/BDK1/ERSS/STL/DT1 TO DT4
Drawing Title :
GEOTECHNICAL
LAYOUT PLAN FOR PHASE 1
PRO FE
SCALE 1:75
SHEET PILING AND STRUTTING
R EE IN
TYPICAL STRUTTUNG (TYPE 1)
L E A ON N SI G S
DR LI GUOJUN 4367 S
E I NG APOR
DESIGNED :
DRAWN :
JOB NO :
06 APR.2016 Date
CHECKED : RM
AY SCALE :
15016
AS SHOWN
WRX
DATE : 23 OCT. 2015
DRAWING NO. :
15016/CWD/BDK/ERSS/FP1-11
REV.
-
THE OWNERSHIP OF THE COPYRIGHT IN THIS DRAWING IS RETAINED BY WRX ENGINEERS WHOSE WRITTEN CONSENT MUST FIRST BE OBTAINED BEFORE ANY USE OR REPRODUCTION OF THE DRAWING OR ANY PART THEREOF TO BE MADE.
sheet of
12
N
N
5
N
BUILDING AND CONSTRUCTION 1689
1690 1695
AUTHORITY
1691
APPROVED UNDER SECTION 5/SECTION 5A OF THE BUILDING CONTROL ACT (CAP 29)
1692 1694
1693 1696
1356
1355
1354 1353
1352
1351
1350
1359
1349
1697 1360
1348
1698
1361
1479 1347 1346 1475
Project Ref No: E3440-00010-2014-ST100 1535 1514
1357
1486 1515 1534
1485
1484
1687
1474
1532 1517
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
6000
20 16 33
6000
R
6000
80 8
A
1433
O
1435
EB
EB
D
1533 1516
6000
1473
I C
E
1472
1686
R
V
1358
E
1685 1684
1471 1553 1552 1470
S
EB EB
EB
1562 1563
K
1555
Y
A
A
P
R
1531 1518
1547
1546
PHASE 1
S
K
T
W
1519 1530
1469 1683
1520 1529
A
O
P
C
R
A
1610
1682
1681 1611 1680
22584
T
T
S
S
1528 1521
6000
1468
6000
6000
6000
6000
6000
CB r RB
2235
RB
KP
RB
CB r
T S L-
KP
T S L-
5992 1011
T S L-
KP
KP
T S L-
T1 S T1 S 1 T S 1012
6000
6000
6000
6000
6000
6000
6000
6000
6000
06 APR.2016 Date
1071
1154
B
6000
E I NG APOR
2996
KP
B
6000
S
2996 3995
RB
KP
2235
CB r
T S L-
r CB
r CB
6000
WU RUIXIN
5992
RB
DRAI NAGERESERVEL I NE
6000
6000
CIVIL
KP
RB
Br C
C Br
5992
CB r
CB r RB
L E A ON N SI G S
3875
CB r
RB
RB
CB r
C Br
RS1
RS1
RS1
RS1
RS1
RS1
RS1
RB
RB
KP
r CB
RS1
RB
r CB
RS1
RB
DRAI NAGERESERVEL I NE
6000
B
1013
Br C
15 113
ST L-
ST L-
ST L-
RB KP
6000
Date
5992
RB
CB r
12000
RB
12000
60 00
60 00
3995 2996 5992 5992
SL 1014
r CB
60 00
RB
r CB
00 120
ST L-
ST L-
ST L-
ST L-
RB
KP
6000
06 APR.2016
Qualified Person Endorsement :
KP
1216
6000
BUILDING CONTROL ACT SINGAPORE
5992
CB r
CB r
1015
ST CB L r
LST
LST
LST
LST
LST
CB r
LST
LST
LST
LST
C Br
LST
C Br
LST
LST
12000
RB
SL
370530003000300030004000
In AC Organization Registration No. A029
5992
C Br
12000 12000
60 00 60 00 60 00 60 00
KP
1212
1215
CHAN EWE JIN
5095
C Br
RS1
RS1
RS1
RS1
RS1
RS1
RS1
RS1
B
B
RS1
S A
Lo ng
KP
1155
1231
NO: 1152
1002
KP RB
RB
1153 1152
1110 1111
ACCREDITED CHECKER
R EE IN
21 m
KP
r CB
RB r CB
FS P I V
r CB
r CB
Br C
KP
RB
ST L-
36 70 30 00 30 00 30 00 30 00 40 00
r CB
B
ST L-
Pi pe
ST L-
r CB
B R
KP
KP
RB
RB
RB
B R
Accredited Checker Endorsement :
KP
KP
KP
1 ST 1 ST 1 ST 1 ST 1 ST
1022
RB
RB
RB
RB
RB
RB
KP
RB
KP
RB
1001
00 120
(
-
1020
)
RB
RB
KP
RB
RB
Br C
1 4 S 31 R 11
1019
1000
RB
RB r CB
1 S R
1 S R
1719
1119 1122 1114 1123 1117
1337 1338
1021
6000
1 ST 1 ST 1 ST
RB
RB
1 S R
1 S R
1718
1461
1460
1107 1106 1108 1105
1121
6000
ST L-
RB
RB
1 S R
1463 1462
1459 1120
6000
DRAI NAGERESERVEL I NE
Br C
1 S R
1 S R
1 S R
1 S R
1465 1464
1323
1326
1118
6000
ST L-
1255
1150 1149
1113
6000
ST L-
1253 1254
1109 1115 1116
6000
r CB
E
6000
r CB
1 S R
1709
1324
6000
SL
Br C
1 S R
1466
1325
6000
TH
DRAI NAGERESERVEL I NE
1256
6000
PRO FE
6000
6000
6000
CB r
PA
6000
CB r
A E
T
6000
T
C
FO
O
6000
CB r
A O
1467
2996
6000
1527 1522
1213
1117
1119
1118
1116
1115
1114
FSP-IV (14m Long)
FSP-IV (21m Long)
1236
1235
1234 1177
6000
6000
6000
6000
6000
4000 300030002600
Description
Rev Date
1178 1230 1780
1779
1179 1778
MAIN CONTRACTOR:
1777
N
1797
1180
UNDER ST100 (THIS) SUBMISSION
1229
1907
1228 1908 1776
1798
1181
SHEET PILING AND STRUTTING LAYOUT PLAN FOR PHASE 2
42D Penjuru Road Singapore 609162 Tel: +65 6898 5225
Fax: +65 6898 5156
SCALE 1:500 Consultant :
STEEL MEMBER SCHEDULE
KING POST SCHEDULE
WRX ENGINEERS Pte.Ltd. TYPE
SIZE
STEEL GRADE
PILE SIZE
REFERENCE PILE LENGTH TOE LEVEL BOREHOLE FROM RL95.0m (m) (mRL)
SL
WALER FOR LACED STRUT
UC 400x400x147 Kg/m
S355
UC 300x300x94 kg/m
ABH1
8.00
87.00
L-ST
LACED STRUT
2UC 300x300x94 Kg/m
S355
UC 300x300x94 kg/m
ABH2
13.00
82.00
KP
KINGPOST
UC 300x300x94 Kg/m
S275
UC 300x300x94 kg/m
ABH3
13.00
82.00
RS
RAKER STRUT
UC 400x400x197 Kg/m
S355
UC 300x300x94 kg/m
ABH4
14.90
81.00
WS
WALER FOR RAKER STRUT
UC 400x400x283 Kg/m
S355
UC 300x300x94 kg/m
ABH5
13.50
81.50
RB
RUNNER BEAM
UC 300x300x106 Kg/m
S275
UC 300x300x94 kg/m
ABH6
16.00
79.00
CBr
CROSS BRACING
UC 150x150x31 Kg/m
S275
UC 300x300x94 kg/m
ABH7
14.00
81.00
ST1
SINGLE STRUT
UC 300x300x94 Kg/m
S275
UC 300x300x94 kg/m
ABH8
15.00
80.00
UC 300x300x94 kg/m
ABH9
21.00
74.00
UC 300x300x94 kg/m
ABH10
21.00
74.00
UC 300x300x94 kg/m
ABH11
14.00
81.00
UC 300x300x94 kg/m
ABH12
6.00
89.00
UC 300x300x94 kg/m
ABH13
6.00
89.00
UC 300x300x94 kg/m
ABH14
6.00
89.00
UC 300x300x94 kg/m
ABH15
6.00
89.00
(CIVIL & STRUCTURAL ENGINEERING CONSULTANTS) 190 Middle Road, #18-05, Fortune Centre
SPECIALIST ACCREDITED CHECKER
Singapore 188979 Tel 62727071 Fax 62787071 Email :
[email protected]
NO: 7033 CATCHMENT AND WATERWAYS
FOR CONNECTION DETAIL, REFER TO DRAWING NO. 15016/CWD/BDK1/ERSS/STL/DT1 TO DT4
LAU WEI HING BUILDING CONTROL ACT SINGAPORE
Project Title :
IMPROVEMENT OF BEDOK CANAL BETWEEN EAST COAST PARKWAY AND THE SEA ON
06 APR.2016
LOT05673P PT, LOT09870X PT, MK 27, AT
Date
EAST COAST PARKWAY
Drawing Title :
SHEET PILING AND STRUTTING
GEOTECHNICAL
LAYOUT PLAN FOR PHASE 2
R EE IN
L E A ON N SI G S
PRO FE
NOTE:
DEPARTMENT
DR LI GUOJUN 4367 S
E I NG APOR
DESIGNED :
DRAWN :
JOB NO :
06 APR.2016 Date
CHECKED : RM
AY SCALE :
15016
AS SHOWN
WRX
DATE : 23 OCT. 2015
DRAWING NO. :
15016/CWD/BDK/ERSS/FP1-21
REV.
-
THE OWNERSHIP OF THE COPYRIGHT IN THIS DRAWING IS RETAINED BY WRX ENGINEERS WHOSE WRITTEN CONSENT MUST FIRST BE OBTAINED BEFORE ANY USE OR REPRODUCTION OF THE DRAWING OR ANY PART THEREOF TO BE MADE.
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
18of 24
APPENDIX C ATTACHMENT: SILENT PILER MACHINE MODEL ECO100 CATALOGUE
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
19of 24
APPENDIX D ATTACHMENT: SILENT PILER MACHINE MODEL SA100 CATALOGUE
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
20of 24
APPENDIX E ATTACHMENT: SILENT PILER MACHINE MODEL SA150 CATALOGUE
Construction Revolution Guide Vol. 3
ed from Giken's corporate home page at http://www.giken-smp.com/
Machine Specifications
Metric Unit
Silent Piler
400
U Profile Steel Sheet Pile
SUPER AUTO
mm
1000
Crawler is optional equipment.
MAX 3380
475 1030
2580
2060
U Profile 400 mm Max. Installation Force 1 500 kN Max. Extraction Force 1 600 kN Stroke 850 mm Pressing-in Speed 1.0 - 23.2 m/min Drawing-out Speed 2.1 - 16.2 m/min Operation Radio Control Movement Self-moving Total Weight 7 740 kg Power Pack Sheet Pile Range
570 1600
2100
1705
4150
4724
1770
Reaction Stand
3380
470
6220
2350
1780
Power Pack
Engine Unit Type EU 200 Power Source Diesel Engine Rated Output 147 kW (200 PS) Fuel Tank 350 L Hydraulic Oil 550 L Noise Level at 7m 69 dB (A) Weight 4 900 kg Crawler Type GT1 (Optional) Crawler Operation Remote Control Power Source 2 Pumps x 2 Motors Moving Speed 1.4 km/h Weight 1 000 kg Total Weight 5 900 kg Reaction Stand Weight 1 700 kg * Specifications are subject to alteration without prior notice.
For further information on The Giken Silent Piler, please ;
U. S. A
Giken America Corporation
The Netherlands U. K.
Tel. +1-407-380-3232
Fax +1-407-380-9411
Giken Europe B.V. Head Office
Tel. +31-(0)36-532-8128
Fax +31-(0)36-532-7477
Giken Europe B.V. London Office
Tel. +44-(0)20-8461-6620
Fax +44-(0)20-8461-6621
Giken Europe B.V. Berlin Office
Tel. +49-(0)30-4702-3380
Fax +49-(0)30-4702-3382
Singapore
Giken Seisakusho Asia Pte., Ltd.
Tel. +65-863-0330
Fax +65-863-1141
Japan
Giken Seisakusho Co., Ltd.
Tel. +81-(0)3-3528-1630
Fax +81-(0)3-3527-6055
Copyright © Giken Seisakusho Co., Ltd. All Rights Reserved.
Ver. 1.0
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
21of 24
APPENDIX F ATTACHMENT: SHEET PILE FABRICATION DETAILS
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
22of 24
APPENDIX G ATTACHMENT: WELDING PROCEDURE SPECIFICATIONS
OWNER/CLIENT CONTRACT No. PROJECT TITLE PROJECT LOCATION MAIN CONTRACTOR SUB-CONTRACTOR
: : : : : :
PUB CATCHMENT AND WATERWAYS DEPARTMENT C1 IMPROVEMENT OF BEDOK CANAL EAST COAST PARKWAY HSL CONSTRUCTOR PTE LTD STEADFAST ENGINEERING & CONSTRUCTION
SUMMARY LIST OF WPS & PQR
Revision : 01
Base Metal S/N
WPS & PQR No.
Welding Process
Material Spec.
P No.
Group Thickness No. Range (mm)
Filler Metal
Argon Gases
Impact Test
Pre-Heat
Post-Heat
PWHT
No.
Process
SFA No.
F No.
AWS Class No.
Rod Ø (mm)
Trade Name
Shield (L/min)
Back (L/min)
Temp.(ºc)
Temp.(ºc)
Temp.(ºc)
Temp. Range(ºC)
Holding Time(Hr)
Remarks
1
WPS/HSL/01/06 PQT/01/06
Carbon Steel ASTM A36
1 to 1
1 to 1
3 to 25.4
All
SMAW
5.1
4
E7016
1.6 to 5.0
Kobe LB-52
N.A
N.A
N.A
N.A
N.A
N.A
N.A
4G PLATE AWS D1.1
2
WPS/HSL/10/06 HSL/PQR/10/06
Carbon Steel ASTM A36
1 to 1
1 to 1
3mm to Unlimited
All
SMAW
5.1
4
E7016
1.6 to 5.0
Kobe LB-52
N.A
N.A
N.A
N.A
N.A
N.A
N.A
2G PLATE AWS D1.1
3
WPS/HSL/11/06 HSL/PQR/11/06
Carbon Steel ASTM A36
1 to 1
1 to 1
3mm to Unlimited
All
SMAW
5.1
4
E7016
1.6 to 5.0
Kobe LB-52
N.A
N.A
N.A
N.A
N.A
N.A
N.A
3G PLATE AWS D1.1
4
WPS/HSL/05/06 PQR/HSL/05/06
Carbon Steel ASTM A36
1 to 1
1 to 1
3mm to Unlimited
All
FCAW
5.2
-
E 71T-1
1.2 to 5.0
FUJI FW-100
N.A
N.A
N.A
250ºC
N.A
N.A
N.A
2G PLATE AWS D1.1
5
WPS/HSL/06/06 PQR/HSL/06/06
Carbon Steel ASTM A36
1 to 1
1 to 1
3mm to Unlimited
All
FCAW
5.2
-
E 71T-1
1.2 to 5.0
FUJI FW-100
N.A
N.A
N.A
250ºC
N.A
N.A
N.A
3G PLATE AWS D1.1
STEADFAST ENGINEERING CONSTRUCTION
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
10-0115P025-MS-015
Rev. No.
3
Date
15/02/2017
Page
23of 24
APPENDIX H ATTACHMENT: LIFTING PLAN
JOB No.
DOC No.
REV.1
10-0115P025-LP-007
Lifting Plan
Page 1 of 11
Date: 1 Nov 2016
PROJECT TITLE/ WO No:
Bedok Canal Improvement C1 Project
CLIENT:
PUB
LIFT PLAN TITLE:
ERSS Lifting Plan, Bedok Canal C1
LIFT CLASSIFICATION Please tick √ the appropriate box Standard Lift
Non Standard Lift
Critical Lift
< 39M
Circle radius = Working Boom Length + Load Protrusion NAME
PREPARED BY Yeu Wee Chek (Planning Engineer)
REVIEWED BY Islam Mohammed Amirul (Lifting Supervisor)
APPROVED BY Lim Seong San (Project Manager)
1 Nov 2016
1 Nov 2016
1 Nov 2016
SIGNATURE
DATE
Crane Access
Zone A
Lifting Zone
10-0115P025-LP-007
DOC No.
Zone B
Lifting Zone
Date: 1 Nov 2016
Zone D
Lifting Plan
JOB No.
Zone C
Page 2 of 11
REV.1
JOB No.
DOC No.
REV.1
10-0115P025-LP-007
Lifting Plan
Date: 1 Nov 2016
Page 3 of 11
Table of Contents 1.
Introduction ........................................................................................................................................................... 4
2.
Procedure ............................................................................................................................................................... 4
3.
Load Details (Calculation and Working Range) ........................................................................................... 6
4.
Rigging Method .................................................................................................................................................... 9
5.
Plot Plan ............................................................................................................................................................... 10
JOB No.
DOC No.
REV.1
10-0115P025-LP-007
Lifting Plan
Date: 1 Nov 2016
Page 4 of 11
1. Introduction • This document proposes the methods to be used for the Lifting Sheet pile • This lifting plan covers only the lifting operations 1.1. Equipment IHI CCH650 Crane 1.2. Load Details 1.2.1. Sheet piles FSP IV 9m, 12m,14m, 18m :1600 kg (Estimated Heaviest Load) 2. Procedure Mobilization and Demobilization 1) Check and plan the travel routes prior mobilization of equipment to job site 2) Ensure travel routes and accesses to the job site are in good condition 3) Equipment to enter and occupy ERSS stockpile location to crane set up location 4) Banks-man to assist driver / crane operator in guiding for blind spots when safe moving of equipment 5) To set up the crane and position at ERSS stockpile location (as per plot plan) Preparation for lifting operation 1) Lifting supervisor to brief riggers, signalman and crane operators of the cranes lifting procedures for the Lifting Sheet pile, ERSS stockpile location shall coordinate with the site supervisor throughout the entire lifting operations 2) Barricades and displays warning signage within the crane working area 3) Riggers to check all lifting gears are in good condition and the correct sizes are used. Valid inspection for LM, LG, LA shall be in order 4) Crane operator to check the body, structures and devices of the crane component for any defects or malfunctions 5) Crane operator to ascertain the ground condition, weight of the load and lifting radius, and must also comply strictly in accordance with Lifting Checklist when setting up the crane 6) Signalman to check and ensue all cranes’ working area or load destination is free from obstacles or obstructions for safe moving before any lifting is to be carried out 7) Signalman and crane operator must have the common understanding in accordance with the standard signaling when lifting is carrying out. Radio communication or hand signal shall be used for the lifting operation 8) Lifting supervisor is responsible to ensure crane operator, riggers and signalman fully complied with all the crane lifting procedures throughout the entire lifting operations 9) Lifting gears to be used as follows; a. 1 pc 1-1/8’’ A-344 Type Masterlink
JOB No.
DOC No.
REV.1
10-0115P025-LP-007
Lifting Plan
Date: 1 Nov 2016
Page 5 of 11
b. 2 pcs 3/8’’ S1325 Type Chain Coupler c. 2 lengths ½’’ x 20ft Alloy Chain d. 2 pcs ½’’ A339 Type Clevis Sling Hook w/ Latch Kit Lifting procedure 1) To set up 50 tons crane and position at ERSS stock pile location (as per plot plan) 2) Attached all lifting gears crane hook block, swing and lower down the crane boom until crane hook block top of the location and stop. 3) Rigs and secured lifting gears onto the load. 4) Used 2 tag line to control and minimize load movement 5) Lifting supervisor and crane operator shall counter check on the crane stability when the crane has totally taken off the load 6) When load is clear from any obstruction crane boom slowly hoist up and swing from initial position west to north by anti-clockwise direction as attached plot plan 7) Slowly lower the load onto the ground 8) Remove lifting gears 9) Demobilize the crane and perform proper housekeeping
Lifting Material Adding 10% of the load Hook block weight Total Load Boom Length Working Radius Safe Working Load Safety Factor Crane capacity use
: 1600 kg (Heaviest) : 1760 kg : 600 kg (inclusive of lifting gears) : 2360 kg : 42 M : 26 M : 4650 kg : 4650 kg / 2360 kg = 1.97 : 2360 kg / 4650 kg % = 50.7%
Load Data Calculations Heaviest Load
3. Load Details (Calculation and Working Range)
Lifting Plan
10-0115P025-LP-007
DOC No.
Date: 1 Nov 2016
JOB No.
Page 6 of 11
REV.1
Lifting Plan
10-0115P025-LP-007
DOC No.
Date: 1 Nov 2016
JOB No.
Page 7 of 11
REV.1
JOB No.
DOC No.
REV.1
10-0115P025-LP-007
Lifting Plan
Date: 1 Nov 2016
Page 8 of 11
JOB No.
DOC No.
REV.1
10-0115P025-LP-007
Lifting Plan
Date: 1 Nov 2016
Page 9 of 11
4. Rigging Method
2-legged chain sling 2 pcs A399 clevis sling hook Safe work loading: 5000kg
20m
20m
60 degrees
60 degrees
Sheet Pile 21m
Plot Plan
B A
C
Zone A
360°swing radius with 20m working radius
(C)→ Swing Radius Radius= 20m (max) Boom Length= 40m
(B)→ Drop off point Radius= 20m
(A)→ Pick up point Radius= 20m
5.
B Zone D
C
Zone B
Lifting Plan
A
B A
C A
10-0115P025-LP-007
DOC No.
Date: 1 Nov 2016
JOB No.
C
A
B
C
Zone C
Page 10 of 11
REV.1
B
JOB No.
DOC No.
REV.1
10-0115P025-LP-007
Lifting Plan
Date: 1 Nov 2016
Page 11 of 11
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Page 1 of 12
Date: 6 May 2016
PROJECT TITLE/ WO No:
Bedok Canal Improvement C1 Project
CLIENT:
PUB
LIFT PLAN TITLE:
ERSS Lifting Plan, Bedok Canal C1
LIFT CLASSIFICATION Please tick √ the appropriate box Standard Lift
Non Standard Lift
Critical Lift
< 39M
Circle radius = Working Boom Length + Load Protrusion NAME
PREPARED BY Yeu Wee Chek (Planning Engineer)
REVIEWED BY Loh Kin Chuen (Lifting Supervisor)
APPROVED BY Lim Seong San (Project Manager)
17 Mar 2016
17 Mar 2016
17 Mar 2016
SIGNATURE
DATE
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 6 May 2016
Lifting Zone
Lifting Zone
Crane Access
Page 2 of 12
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 6 May 2016
Page 3 of 12
Table of Contents 1.
Introduction ........................................................................................................................................................... 4
2.
Procedure ............................................................................................................................................................... 4
3.
Load Details (Calculation and Working Range) ........................................................................................... 6
4.
Rigging Method .................................................................................................................................................... 9
5.
Plot Plan ............................................................................................................................................................... 11
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 6 May 2016
Page 4 of 12
1. Introduction • This document proposes the methods to be used for the Lifting Sheet pile • This lifting plan covers only the lifting operations 1.1. Equipment KOLBECO CKE800G (80T) 1.2. Load Details 1.2.1. Sheet pile <1600 kg 1.2.2. Lifting Hook 600kg+ Sheet pile 1600kg – Estimated Heaviest Load = 2200kg Note: All the loading objects shall be stated here. Must assign the wording of “Estimated Heaviest Load” to the heaviest load of the work activity. 2. Procedure Mobilization and Demobilization 1) Check and plan the travel routes prior mobilization of equipment to job site 2) Ensure travel routes and accesses to the job site are in good condition 3) Equipment to enter and occupy ERSS location to crane set up location 4) Banks-man to assist driver / crane operator in guiding for blind spots when safe moving of equipment 5) To set up the crane and position at ERSS location (as per plot plan) Preparation for lifting operation 1) Lifting supervisor to brief riggers, signalman and crane operators of the cranes lifting procedures for the Lifting Sheet pile, ERSS location shall coordinate with the site supervisor throughout the entire lifting operations 2) Barricades and displays warning signage within the crane working area 3) Riggers to check all lifting gears are in good condition and the correct sizes are used. Valid inspection for LM, LG, LA shall be in order 4) Crane operator to check the body, structures and devices of the crane component for any defects or malfunctions 5) Crane operator to ascertain the ground condition, weight of the load and lifting radius, and must also comply strictly in accordance with Lifting Checklist when setting up the crane 6) Signalman to check and ensue all cranes’ working area or load destination is free from obstacles or obstructions for safe moving before any lifting is to be carried out 7) Signalman and crane operator must have the common understanding in accordance with the standard signaling when lifting is carrying out. Radio communication or hand signal shall be used for the lifting operation 8) Lifting supervisor is responsible to ensure crane operator, riggers and signalman fully
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 6 May 2016
Page 5 of 12
complied with all the crane lifting procedures throughout the entire lifting operations 9) Lifting gears to be used as follows; a. 1no x 8m Lifting Chain b. 1no x 8.5ton shackle c. 1no x 1.5m xx20mm x 5ton Steel Wire Rope both end 12’’ eye Lifting procedure 1) To set up 80 tons crane and position at ERSS location (as per plot plan) 2) Attached all lifting gears crane hook block, swing and lower down the crane boom until crane hook block top of the location and stop. 3) Rigs and secured lifting gears onto the load. 4) Used 2 tag line to control and minimize load movement 5) Lifting supervisor and crane operator shall counter check on the crane stability when the crane has totally taken off the load 6) When load is clear from any obstruction crane boom slowly hoist up and swing from initial position west to north by anti-clockwise direction as attached plot plan 7) Slowly lower the load onto the ground 8) Remove lifting gears 9) Demobilize the crane and perform proper housekeeping
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan 3. Load Details (Calculation and Working Range) Load Data Calculations Heaviest Load Lifting Material Adding 10% of the load Hook block weight Total Load Boom Length Working Radius Safe Working Load Safety Factor Crane capacity use
: 1600 kg (Heaviest) : 1760 kg : 600 kg (inclusive of lifting gears) : 2360 kg : 39 M : 39 M : 3500 kg (7510) : 3500 kg / 2360 kg = 1.48 : 2360 kg / 3500 kg % = 67.4%
Date: 6 May 2016
Page 6 of 12
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 6 May 2016
Page 7 of 12
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 6 May 2016
Page 8 of 12
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan 4. Rigging Method
< 39M
Date: 6 May 2016
Page 9 of 12
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Page 10 of 12
Date: 6 May 2016
Wire rope 5tons
8.5 tons shackle
FSPIV Sheet Pile
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
5.
Date: 6 May 2016
Page 11 of 12
Plot Plan
360°swing radius with 21m working radius
C B A (A)→ Pick up point Radius= 21m (B)→ Drop off point Radius= 21m (C)→ Swing Radius Radius= 21m (max) Boom Length= 39m
C B A
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 6 May 2016
Page 12 of 12
6. Ground bearing You may refer to attachment in the next section for the ground bearing capacity check that is duly endorsed by Professional Engineer.
TABLE OF CONTENTS
PAGES
1.0
INTRODUCTION
1
2.0
DESIGN INFORMATION
1
ANNEX 1
ANALYSIS AND DESIGN
2-4
ANNEX 2
REFERENCES
5
i.
SECTION AND BORELOGS
6-8
ii.
TYPE OF CRANES
9-32
1
1.
INTRODUCTION This design calculation presents the professional Engineer’s check of soil bearing capacity for clawer crane access at Improvement of Bedok Canal between East Coast Parkway and the Sea on Lot 05673P PT, LOT 09870X PT, MK27, at East Coast Parkway. The access area consist of 6m x 6m x 25mm thick steel plate sit on existing ground level to cater maximum 80 tons clawer crane with lifting load for moving and parking.
2.
DESIGN INFORMATION STANDARDS & CODES OF PRACTICE The following SS or BS Standards / Codes of Practice are used and / or referred in the design. BS 5950-1: 2000 SS 4: 2003
Structural Use of Steelwork in Building Code of Practice for Foundations
MATERIAL SPECIFICATIONS Steel Plate
S275 or G43 Steel
Plate thickness ≤ 16mm Plate thickness > 16mm
275 N/mm2 265 N/mm2
KEY CONSIDERATIONS
Maximum Crane Load + Lifting load : 75.1+1.6 (21m of FSPIV) = 76.7 ton ~ 80 ton
Superimposed Load : 10 kN/m2
Type of Crane : CKE800G Clawer Crane (Refer to Annex 2)
Dead loads (self weight) of materials used in the design Steel: 78.5 kN/m3
9
TYPE OF CRANES
10
Hydraulic Crawler Crane
Model : CKE800G Max. Lifting Capacity : 80 t x 3.0 m Max. Crane Boom Length : 54.9 m Max. Fixed Jib Combination: 42.7 m + 18.3 m 45.7 m + 12.2 m
11
CKE800G CONTENTS
3
:7,*0-0*(;065:
5
.,5,9(3+04,5:065:
6
)664(5+10)(99(5.,4,5;:
7
>69205.9(5.,:
10
:<773,4,5;(3+(;(
11
30-;05.*(7(*0;0,:
14
:<773,4,5;(3+(;(-69*3(4:/,33
15
30-;05.*(7(*0;0,:
16
:<773,4,5;(3+(;(-699,+<*,+>,0./;:
17
30-;05.*(7(*0;0,:
18
;9(5:769;(;06573(5
21
7(9;:(5+(;;(*/4,5;: +
12
SPECIFICATIONS Power Plant Model: HINO J08E-UV Type: 4 cycle, water-cooled, vertical in-line 6, direct injection, turbo-charger, intercooler Complies with NRMM (Europe) Stage IIIB and US EPA Interim Tier 4 Displacement: 7,684 liters Rated power: 213 kW/2100 min-1 Max. Torque: 1,017 N·m/1,600 min-1 Cooling System: Water-cooled Starter: 24V-5kW Radiator: Corrugated type core, thermostatically controlled Air cleaner: Dry type with replaceable paper element Throttle: Twist grip type hand throttle, electrically actuated Fuel filter: Replaceable paper element Batteries: Two 12V x 136 Ah/5HR capacity batteries, series connected Fuel tank capacity: 400 liters
Hydraulic System Main pumps: 3 variable displacement piston pumps Control: Full-flow hydraulic control system for infinitely variable pressure to all winches, propel and swing. Controls respond instantly to the touch, delivering smooth function operation. Cooling: Oil-to-air heat exchanger (plate-fin type) Filtration: Full-flow and by type with replaceable element Max. relief valve pressure: Load hoist, boom hoist and propel system: 31.9 MPa Swing system: 27.5 MPa Control system: 5.4 MPa Hydraulic Tank Capacity: 440 liters
Boom Hoisting System Powered by a hydraulic motor through a planetary reducer. Brake: A spring-set, hydraulically released multiple-disc brake is mounted on the boom hoist motor and operated through a counter-balance valve. Drum Lock: External ratchet for locking drum Drum: Single drum, grooved for 16mm dia. wire rope Line Speed: Single line on first drum layer Hoisting/Lowering: 70 to 2 m/min Boom hoisting/lowering: 16 mm x 150 m (5/8 in. x 492 ft) Boom guy line: 30 mm (1-3/16 in.) Boom backstops: Required for all boom length
Load Hoisting System Front and rear drums for load hoist powered by a hydraulic variable plunger motors, driven through planetary reducers. Negative Brake: A spring-set, hydraulically released multiple-
,
disc brake is mounted on the hoist motor and operated through a counter-balance valve. (Positive free fall brake is optional) Drum Lock: External ratchet for locking drum Drums: Front Drums: 550 mm P.C.D x 545 mm wide drum, grooved for 22 mm wire rope. Rope capacity is 220 m working length and 335 m storage length. Rear Drum: 550 mm P.C.D x 545 mm grooved for 22 mm wire rope. Rope capacity is 130 m working length and 335m storage length. Diameter of wire rope Main winch: 22 mm x 220 m Aux. winch: 22 mm x 130 m Third winch: 22 mm x 145 m Line Speed*: Hoisting/lowering: 120 to 3 m/min Line Pull: Max. Line Pull*: 153 kN {15.5 tf} (Referential performance) Rated Line Pull: 78 kN {8.0 tf} *Single line on first drum layer
Swing System Swing unit is powered by hydraulic motor driving spur gears through planetary reducer, the swing system provides 360° rotation. Swing parking brakes: A spring-set, hydraulically released multiple-disc brake is mounted on swing motor. Swing circle: Single-row ball bearing with an integral internally cut swing gear. Swing lock: Manually, four position lock for transportation Swing Speed: 4.0 min-1
Upper Structure Torsion-free precision machined upper frame. All components are located clearly and service friendly. Engine will with low noise level. Counter weight: 27.2 ton
Cab & Control Totally enclosed, full vision cab with safety glass, fully adjustable, high backed seat with a headrest and armrests, and intermittent wiper and window washer (skylight and front window). Cab fittings: Air conditioner, convenient compartment (for tool), cup holder, cigarette lighter, sun visor, roof blind, tinted glass, floor mat, footrest, and shoe tray
13
Lower Structure Steel-welded carbody with axles. Crawler assemblies can be hydraulically extended for wide-track operation or retracted for transportation. Crawler belt tension is maintained by hydraulic jack force on the track-adjusting bearing block. Carbodyweight: 6.5 ton Crawler drive: Independent hydraulic propel drive is built into each crawler side frame. Each drive consists of a hydraulic motor propelling a driving tumbler through a planetary gear box. Hydraulic motor and gear box are built into the crawler side frame within the shoe width. Crawler brakes: Spring-set, hydraulically released parking brakes are built into each propel drive. Steering mechanism: A hydraulic propel system provides both skid steering (driving one track only) and counter-rotating steering (driving each track in opposite directions). Track rollers: Sealed track rollers for maintenance-free operation. Shoe (flat): 800 mm wide each crawler Max. gradeability: 40%
Weight Including upper and lower machine, 27.2 ton counterweight and 6.5 ton carbody weight, basic boom (or basic boom + basic jib), hook, and other accessories. Weight: 75.1 ton Ground pressure: 84.7 kPa
Attachment Boom & Jib: Welded lattice construction using tubular, high-tensile steel chords with pin connection between sections.
Boom and Jib length Min. Length (Min. combination) Crane Boom Fixed Iib
Max. Length (Max. combination)
9.1 m
54.9 m
30.5 m + 6.1 m
42.7 m + 18.3 m, 45.7 m + 12.2 m
Main Specifications (Model: CKE800G) Crane Boom Max. Lifting Capacity 80 t x 3.0 m Max. Length 54.9 m Fixed Jib Max. Lifting Capacity 7.0 t x 20.0 m Max. Combination 42.7 m + 18.3, 45.7 m +12.2 m Main & Aux. Winch Max. Line Speed (1st layer) 120 m/min Rated Line Pull (Single line) 78 kN {8.0 tf} Wire Rope Diameter 22 mm Wire Rope Length 220 m (Main), 130 m (Aux.) Brake Type (Free fall) Wet-type multiple disc brake (Optional) Working Speed Swing Speed 4.0 min-1{rpm} Travel Speed 1.7/1.1 km/h Power Plant Model HINO J08E-UV Engine Output 213 kW/2100 min-1 Fuel Tank 400 liters
Hydraulic System Main Pums Max. Pressure Hydraulic Tank Capacity Self-Removal Device
3 variable displacement 31.9 Mpa {325 kg/cm2} 440 liters Counterweight/self-removal device
Weight Operating Weight Ground Pressure Counterweight Transport Weight
75.1 t *1 84.7 kPa 27,200 kg 39,850 kg *2
Units are SI units. { } indicates conventional units. Line speeds in table are for light loads. Line speed varies with load. *1 Including upper and lower machine, 27.2 ton counterweight, 6.5 ton carbody weight, basic boom, hook, and other accessories. *2 Base machine with boom base, gantry, crawlers, and wire ropes (front/boom hoist)
-
14
GENERAL DIMENSIONS
800
3,500
(Unit: mm)
,3 R4
00
.9
1
OM
5,140 3,160
C SI BA
1,100
9.
m
to
m
54
BO
2,990 1,495
1,750
390
2,080 1,100
3,300
6,170
940
5,440
3,500 (CRAWLER RETRACTED)
6,280
5,130 (CRAWLER EXTENDED)
This catalog may contain photographs of machines with specifications, attachments and optional equipment.
Limit of Hook Lifting
L
.
Hook
L
80 t hook
4.5 m
50 t hook
4.3 m
32 t hook
4.2 m
Hook
L’
19 t hook
4.1 m
Ball hook
3.1 m
L’
15
BOOM AND JIB ARRANGEMENTS Crane Boom Arrangements Boom length m (ft)
Boom length m (ft)
Boom arrangement
9.1 (30)
※
BT
12.2 (40)
※
B 10 T
Boom arrangement
20
30
30
T
B
10 10 20
20
30
30
T
B
10 20
30
T
B
10
30
T
B
39.6 (130) ※
15.2 (50)
18.3 (60)
B
20 T
※
B
10 10 T
※
B
10 20 T 30
B
42.7 (140)
T
※ 20
B
21.3 (70) ※ ※
30
B
10
B
10 10 20 T
※
45.7 (150)
20
30
30
30
T
B
10 10
30
30
30
T
B
10 20
30
30
T
B
10 10 20
30
T
20
30
T
B
10 10
30
T
B
30.5 (100) ※
20
B
10
T
30
T
※
B
10 10 20
51.8 (170)
T
30
T
30
T
54.9 (180)
Symbol B
33.5 (110) ※
※
36.6 (120)
B
20
30
30
T
B
10 10
30
30
T
B
10 10 30
B
10 20
B B B
20
20
B
10 20
B
10 10 20
30 20
30
30
T
30
30
T
20
30
30
30
T
※
B
10 10 20
30
30
30
T
※
B
10 20
B
10 10 20
B
10 20
B
10 10 20
20 T
30
30
48.8 (160)
30
10 10 20
20
B
20 30
B
20
20 T
B
B 10
30
B
B
27.4 (90)
30
T
10 20
B
24.4 (80)
20 T
20
20
30 20
10 20 30 10 10 20
30 30 20
30 30
T
30
T
30
20
20
20
30 20
30
30
30
T
30
30
T
30
10 30
30
T
30
T
Boom Length
Remarks
5.2 m
Boom Base
3.9 m
Boom Top
10
3.0 m
Insert Boom
20
6.1 m
Insert Boom
20
6.1 m
Insert Boom with lug
30
9.1 m
Insert Boom
30
9.1 m
Insert Boom with lug
T
T
20
T
30 T 30
※
20
mark shows the guy line installing position when the fixed jib is used. ※ indicates the most flexible combination of insert luffing booms, which can be modified to form all shorter luffing boom arrangements.
Fixed Jib Arrangements
Fixed Jib
Crane boom length
Jib length m (ft)
Jib arrangement B T
6.1 (20)
3.0
12.2 (40)
B
3.0
30.5 m ∼ 45.7 m BOOM
30.5 m ∼ 42.7 m
18.3 (60)
20
Symbol
T
B T B
20
20
T
20
Jib Length 3.0 m 3.0 m 6.1 m
Remarks Jib Base Jib Top Insert Jib
/
16
WORKING RANGES
Crane Boom
80˚
75˚
70˚
65˚
60˚
55˚
65
50˚
60
54.9m Boom 55
51.8m Boom 48.8m Boom
45˚
50
45.7m Boom 42.7m Boom
45
40
36.6m Boom 35˚
33.5m Boom
35
30.5m Boom 30
27.4m Boom 30˚
24.4m Boom
25 21.3m Boom 18.3m Boom
20
15.2m Boom 12.2m Boom
1.77 m
9.1m Boom
10
15
20
25
30
35
5
Center of rotation 1.1 m
0
Radius from center of rotation (m)
40
45
50
Height above ground (m)
40˚
39.6m Boom
17
Fixed Jib 10° 10° 80° 75
70
65 42.7m Boom + 18.3m Jib 45.7m Boom + 12.2m Jib
60
55
45.7m Boom + 6.1m Jib 30.5m Boom + 18.3m Jib
50
30.5m Boom + 12.2m Jib
40
30.5m Boom + 6.1m Jib
35
30
Height above ground (m)
45
25
1.75 m
20
10
1.1 m
Center of rotation
15
20
25
30
35
40
45
50
Radius from center of rotation (m)
1
18
WORKING RANGES
Fixed Jib 30° 30°
80°
75
70
65 42.7m Boom + 18.3m Jib 60
45.7m Boom + 12.2m Jib
55 45.7m Boom + 6.1m Jib 50
30.5m Boom + 18.3m Jib
45
40 30.5m Boom + 6.1m Jib 35
30
25
1.75 m
20
10
Center of rotation 1.1 m
2
15
20
25
30
35
Radius from center of rotation (m)
40
45
50
Height above ground (m)
30.5m Boom + 12.2m Bib
19
SUPPLEMENTAL DATA · Ratings according to EN13000. · Operating radius is the horizontal distance from centerline of rotation to a vertical line through the center of gravity of the load. · Deduct weight of hook block (s), slings and all other load handling accessories from main boom ratings shown. · Ratings shown are based on freely suspended loads and make no allowance for such factors as wind effect on lifted load, ground conditions, out-of-level, operating speeds or any other condition that could be detrimental to the safe operation of this equipment. The operator, therefore, has the responsibility to judge the existing conditions and reduce lifted loads and operating speeds accordingly. · Ratings are for operation on a firm and level surface, up to 1 % gradient. · At radii and boom lengths where no ratings are shown on chart, operation is not intended nor approved. · Boom inserts and guy lines must be arranged as shown in the "operator's manual". · Boom hoist reeving is 12 part line.
(Crane boom lifting) · The total load that can be lifted is the value for weight of main hook block, slings, and all other load handling accessories deducted from crane boom ratings shown. (Fixed jib lifting) · The total load that can be lifted is the value for weight of jib hook block, slings, and all other load handling accessories deducted from fixed jib ratings shown. · The availability of fixed jib mounting - On crane boom : Range 30.5 m to 45.7 m. But 18.3 m jib is not allowed to install on 45.7 m main boom.
Main hoist loads No. of Parts of Line Maximum Loads (kN) Maximum Loads (t)
1 78 8.0
2 157 16.0
3 235 24.0
4 314 32.0
5 392 40.0
No. of Parts of Line Maximum Loads (kN) Maximum Loads (t)
6 471 48.0
7 549 56.0
8 628 64.0
9 706 72.0
10 785 80.0
Auxiliary hoist loads No. of Parts of Line Maximum Loads (kN) Maximum Loads (t)
· Gantry must be in raised position for all conditions. · Boom backstops are required for all boom lengths.
Hook Block Weight (t)
· The boom should be erected over the front of the crawlers, not
Weight of hook block 50 t 32 t 19 t 0.7 0.5 0.4
Ball Hook 0.16
Operation of this equipment in excess of rated loads or disregard of instruction voids the warranty.
laterally. · Ratings inside of boxes
80 t 0.8
1 69 7.0
are limited by strength of
materials. · The minimum rated load is 1.1 (ton). · Crawler frames must be fully extended for all crane operations.
Assembling the counterweight 27.2 ton counterweight 06.5 ton carbody weight No.4
No.5 No.3 No.2 No.1
· When erecting or lowering the boom length of 54.9 m(180 ft) or over, the blocks for erection must be placed under the front of the crawlers.
Counterweights
Carbody weights
Assembling the counterweight (Equipped with self removal device) 26.1 ton counterweight 06.5 ton carbody weight No.4
No.5
No.2
No.3 No.1 Counterweights
Carbody weights
· The lifting capacity does not change due to the type of counterweights.
*)
20
LIFTING CAPACITIES Counterweight: 27.2 t Carbody Weight: 6.5 t
Crane Boom Lifting Capacities
Unit: metric ton Working radius (m)
Boom Length (m)
3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 Reeves
9.1
12.2
80.0 69.0 57.9 47.5 39.8 32.9 26.0 9.2m/24.5
3.6m/76.2 72.6 57.7 47.3 39.6 32.7 27.8 24.1 11.9m/19.3
10
10
15.2
18.3
4.2m/69.6 57.5 46.7 38.9 32.5 27.6 23.9 18.8 15.4 14.5m/14.7
4.7m/59.3 55.1 44.6 37.3 32.0 27.5 23.8 18.7 15.3 12.9 17.1m/11.8
9
8
21.3
24.4
5.2m/50.0 42.6 35.8 30.9 27.0 23.7 18.6 15.1 12.7 10.9 19.8m/9.6
5.7m/42.9 40.8 34.5 29.8 26.2 23.3 18.5 15.0 12.6 10.8 9.3 8.2 22.4m/8.0
7
6
27.4
30.5
6.3m/37.2 33.3 28.8 25.4 22.6 18.4 14.9 12.5 10.7 9.2 8.1 7.2 25.1m/6.8
6.8m/33.0 32.0 27.8 24.5 21.9 17.9 14.8 12.3 10.5 9.1 7.9 7.0 6.2 27.7m/5.7
5
5
33.5
36.6
7.3m/29.5 26.9 23.8 21.3 17.4 14.7 12.2 10.4 9.0 7.8 6.9 6.1 5.5 4.9 30.3m/4.9
7.9m/26.4 26.0 23.1 20.6 16.9 14.2 12.1 10.3 8.8 7.7 6.8 6.0 5.4 4.8 4.3 33.0m/4.1
4
4
Note: Ratings according to EN13000. Ratings shown in are determined by the strength of the boom or other structural components. Lifting capacities may vary depending on hook used or with/without auxiliary sheave. Please refer rated chart in operator’s cabin.
**
39.6
8.4m/24.0 22.4 20.0 16.5 13.9 11.9 10.2 8.7 7.6 6.6 5.9 5.2 4.7 4.2 3.8 35.0m/3.5
3
42.7
45.7
21.7 19.4 16.0 13.5 11.5 10.0 8.6 7.5 6.5 5.7 5.1 4.5 4.0 3.6 3.3 2.9 38.3m/2.9
9.4m/20.1 19.0 15.6 13.2 11.3 9.8 8.5 7.4 6.4 5.6 5.0 4.4 3.9 3.5 3.2 2.8 2.6 40.9m/2.4
3
3
48.8
51.8
18.4 15.1 12.8 10.9 9.4 8.3 7.2 6.3 5.5 4.9 4.3 3.8 3.4 3.0 2.7 2.4 2.1 43.5m/2.0
10.5m/17.1 14.8 12.5 10.7 9.3 8.1 7.1 6.2 5.4 4.8 4.2 3.7 3.3 2.9 2.6 2.3 2.0 1.8 1.6
3
3
54.9
11.0m/15.7 14.4 12.1 10.4 9.0 7.8 6.9 6.1 5.3 4.7 4.1 3.6 3.2 2.8 2.5 2.2 1.9 1.7 1.5 1.3 48.7m/1.2 2
Boom Length (m)
Working radius (m)
3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 Reeves
21
Fixed Jib Lifting Capacities (Jib Offset Angle : 10°) Boom length (m)
9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
6.1 7.0 7.0 7.0 7.0 7.0 7.0 6.8 6.1 5.4 4.7 4.2 3.8 3.4
1
Boom length (m)
10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
6.1 7.0 7.0 7.0 7.0 7.0 6.6 5.8 5.0 4.4 3.9 3.4 3.0 2.6 2.3 2.0 1.7
1
1
4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.1 3.7 3.3 3.0 2.8 2.5 2.3 2.1 1
39.6 12.2
7.0 7.0 7.0 6.7 6.0 5.3 4.6 4.1 3.6 3.2 2.9 2.5 2.2 1.9 1.7 1.4 1
6.1 7.0 7.0 7.0 7.0 7.0 7.0 6.8 6.0 5.2 4.6 4.1 3.6 3.2 2.9 2.6
7.0 7.0 7.0 7.0 6.9 6.2 5.5 4.8 4.3 3.8 3.4 3.1 2.8 2.5 2.3 2.0
Unit: metric ton
18.3
1
1
4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.4 3.9 3.5 3.2 2.9 2.6 2.4 2.1 1.9 1
18.3
6.1
42.7 12.2
18.3
4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.2 3.7 3.3 3.0 2.7 2.4 2.1 1.8 1.6 1
7.0 7.0 7.0 7.0 6.6 5.7 4.9 4.3 3.8 3.3 2.9 2.5 2.2 1.8 1.6 1.3 1.1 1
7.0 7.0 7.0 6.7 6.0 5.2 4.5 4.0 3.5 3.1 2.8 2.4 2.1 1.8 1.6 1.3 1
4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.1 3.6 3.2 2.9 2.6 2.2 2.0 1.7 1.5 1
6.1 7.0 7.0 7.0 7.0 7.0 6.7 5.9 5.1 4.5 4.0 3.5 3.1 2.8 2.5 2.2
36.6 12.2
1
7.0 7.0 7.0 7.0 6.9 6.2 5.4 4.8 4.2 3.7 3.3 3.0 2.7 2.4 2.1 1.9 1.6 1
6.1
45.7 12.2
7.0 7.0 7.0 7.0 6.5 5.6 4.8 4.2 3.6 3.2 2.7 2.3 2.0 1.6 1.4 1.1 1
7.0 7.0 7.0 6.6 5.8 5.1 4.4 3.9 3.4 3.0 2.6 2.2 1.9 1.6 1.4 1.1 1
Boom length (m)
18.3
4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.3 3.9 3.5 3.1 2.8 2.5 2.3 2.0 1.8 1
Jib length (m)
9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
Boom length (m) Jib length (m)
10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
Working radius (m)
Working radius (m)
Jib length (m)
7.0 7.0 7.0 7.0 7.0 6.4 5.6 5.0 4.4 4.0 3.6 3.2 2.9 2.6
18.3
33.5 12.2
Working radius (m)
Working radius (m)
Jib length (m)
30.5 12.2
Counterweight: 27.2 t Carbody Weight: 6.5 t
Note: Ratings according to EN13000. Ratings shown in are determined by the strength of the boom or other structural components. Lifting capacities may vary depending on hook used or with/without auxiliary sheave. Please refer rated chart in operator’s cabin.
*+
22
LIFTING CAPACITIES Fixed Jib Lifting Capacities (Jib Offset Angle : 30°) Boom length (m)
12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
6.1 7.0 7.0 7.0 7.0 6.9 6.2 5.5 4.8 4.3 3.8
1
Boom length (m)
12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
6.1 7.0 7.0 7.0 7.0 6.6 5.9 5.2 4.5 4.0 3.5 3.1 2.7 2.3 2.0
1
6.1 7.0 7.0 7.0 7.0 6.8 6.1 5.4 4.7 4.2 3.7 3.3
5.0 5.0 5.0 5.0 5.0 5.0 4.5 4.0 3.6 3.2 2.9 2.6
Unit: metric ton
18.3
1
1
1
1
3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.0 2.9 2.8 2.7 2.5 2.3 2.1 1
39.6 12.2
18.3
6.1
42.7 12.2
18.3
5.0 5.0 5.0 5.0 5.0 4.9 4.3 3.8 3.4 3.0 2.7 2.4 2.1 1.8 1.5 1
3.2 3.2 3.2 3.2 3.2 3.2 3.1 3.0 2.8 2.7 2.6 2.5 2.4
3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.1 2.9 2.6 2.3 2.1 1.8 1
7.0 7.0 7.0 6.6 5.9 5.1 4.4 3.9 3.4 3.0 2.6 2.2 1.9 1.6
1
5.0 5.0 5.0 5.0 4.8 4.3 3.8 3.3 3.0 2.6 2.3 2.0 1.7 1.4 1
3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.2 2.8 2.5 2.3 2.0 1.7 1
Note: Ratings according to EN13000. Ratings shown in are determined by the strength of the boom or other structural components. Lifting capacities may vary depending on hook used or with/without auxiliary sheave. Please refer rated chart in operator’s cabin.
*,
6.1 7.0 7.0 7.0 7.0 6.8 6.1 5.3 4.6 4.1 3.6 3.2 2.9
36.6 12.2
5.0 5.0 5.0 5.0 5.0 5.0 4.4 3.9 3.5 3.1 2.8 2.5 2.2
1
1
6.1
45.7 12.2
7.0 7.0 7.0 6.6 5.8 5.0 4.3 3.8 3.3 2.9 2.4 2.1 1.7 1.4 1.2 1
5.0 5.0 5.0 5.0 4.7 4.2 3.7 3.2 2.9 2.5 2.1 1.8 1.5 1.3 1
Boom length (m)
18.3
3.2 3.2 3.2 3.2 3.2 3.2 3.1 3.0 2.9 2.7 2.5 2.2 2.0 1
Jib length (m)
12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
Boom length (m) Jib length (m)
12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
Working radius (m)
Working radius (m)
Jib length (m)
5.0 5.0 5.0 5.0 5.0 4.9 4.6 4.1 3.7 3.3 3.0
18.3
33.5 12.2
Working radius (m)
Working radius (m)
Jib length (m)
30.5 12.2
Counterweight: 27.2 t Carbody Weight: 6.5 t
23
SUPPLEMENTAL DATA FOR CLAMSHELL RATING CHART · Operating radius is the horizontal distance from centerline of rotation to a vertical line through the center of gravity of the load. · Deduct weight of bucket, slings and all other load handling accessories from main boom ratings shown. · Ratings shown are based on freely suspended loads and make no allowance for such factors as wind effect on lifted load, ground conditions, out-of-level, operating speeds or any other condition that could be detrimental to the safe operation of this equipment. The operator, therefore, has the responsibility to judge the existing conditions and reduce lifted loads and operating speeds accordingly. · Rated loads do not exceed 66% of minimum tipping loads. · Ratings are for operation on a firm and level surface, up to 1% gradient. · At radii and boom lengths where no ratings are shown on chart, operation is not intended nor approved. · Boom inserts and guy lines must be arranged as shown in the "operator's manual". · Boom hoist reeving is 12 part line. · Gantry must be in raised position for all conditions. · Boom backstops are required for all boom lengths. · The boom should be erected over the front of the crawlers, not
(Clamshell bucket lifting) · The total load that can be lifted is the value for weight of bucket, slings, and all other load handling accessories deducted from main boom ratings shown. · The weight of bucket and materials must not exceed rated load. · Optimum bucket should be required according to material. Bucket capacity (m3) x specified gravity of material (ton/m3) + bucket weight (ton) = rated load. · Bucket weight must also be decreased according to operating cycle and bucket lowering height. · Rated loads are determined by stability and boom strength. During simultaneous operations of boom and swing, rapid acceleration or deceleration must be avoided. · Do not attempt to cast the bucket while swinging or diagonal draw-cutting.
Main hoist loads No. of Parts of Line Maximum Loads (kN) Maximum Loads (t)
1 69 7.0
Assembling the counterweight 22.8 ton counterweight without carbody weight
laterally. No.3 No.2 No.1
· Crawler frames must be fully extended for all crane operations.
Counterweights
Carbody weights
Assembling the counterweight (Equipped with self removal device) 17.7 ton counterweight without carbody weight No.2
No.3 No.1 Counterweights
Carbody weights
· The lifting capacity does not change due to the type of counterweights.
Operation of this equipment in excess of rated loads or disregard of instruction voids the warranty.
*-
24
LIFTING CAPACITIES Counterweight: 22.8 t Without Carbody Weight Crawler Fully Extended Unit: metric ton
Clamshell Rating Charts Crane Boom Capacities Load radius (m)
Boom length (m)
5.0 5.5 6.0 7.0 8.0 9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
9.1 7.0 7.0 7.0 7.0 7.0 7.0
1
12.2
7.0 7.0 7.0 7.0 7.0
1
Note: Please refer rated chart in operator’s cabin.
*.
15.2
7.0 7.0 7.0 7.0 7.0 7.0
1
18.3
7.0 7.0 7.0 7.0 7.0 7.0
1
21.3
7.0 7.0 7.0 7.0 7.0 7.0
1
Boom length (m)
Load radius (m)
5.0 5.5 6.0 7.0 8.0 9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 Reeves
25
SUPPLEMENTAL DATA FOR REDUCED WEIGHTS RATING CHART · Ratings according to EN13000.
(Crane boom lifting)
· Operating radius is the horizontal distance from centerline of
· The total load that can be lifted is the value for weight of hook
rotation to a vertical line through the center of gravity of the load. · Deduct weight of hook block(s), slings and all other load handling accessories from main boom ratings shown. · Ratings shown are based on freely suspended loads and make no allowance for such factors as wind effect on lifted load, ground conditions, out-of-level, operating speeds or any other condition that could be detrimental to the safe operation of this equipment. The operator, therefore, has the responsibility to judge the existing conditions and reduce lifted loads and operating speeds accordingly. · Ratings are for operation on a firm and level surface, up to 1%
block, slings, and all other load handling accessories deducted from main boom ratings shown. Main hoist loads No. of Parts of Line Maximum Loads (kN) Maximum Loads (t)
1 78 8.0
2 157 16.0
3 235 24.0
4 314 32.0
5 392 40.0
No. of Parts of Line Maximum Loads (kN) Maximum Loads (t)
6 471 48.0
7 549 56.0
8 628 64.0
9 706 72.0
10 785 80.0
Auxiliary hoist loads No. of Parts of Line Maximum Loads (kN) Maximum Loads (t)
gradient. · At radii and boom lengths where no ratings are shown on chart, operation is not intended nor approved.
Hook Block Weight (t)
80 t 0.8
1 69 7.0 Weight of hook block 50 t 32 t 19 t 0.7 0.5 0.4
7.0 t Ball Hook 0.16
· Boom inserts and guy lines must be arranged as shown in the "operator's manual".
Operation of this equipment in excess of rated loads or disregard of instruction voids the warranty.
· Boom hoist reeving is 12 part line. · Gantry must be in raised position for all conditions. · Boom backstops are required for all boom lengths. · The boom should be erected over the front of the crawlers, not
Assembling the counterweight 22.8 ton counterweight without carbody weight
laterally. · Ratings inside of boxes
No.3 No.2 No.1
are limited by strength of
materials.
Counterweights
· The minimum rated load is 1.1(ton). · Crawler frames must be fully extended for all crane operations.
Carbody weights
Assembling the counterweight (Equipped with self removal device) 17.7 ton counterweight without carbody weight No.2
No.3 No.1 Counterweights
Carbody weights
· The lifting capacity does not change due to the type of counterweights.
*/
26
LIFTING CAPACITIES Reduced Weights Rating Charts Crane Boom Lifting Capacities Boom length Load (m) radius (m)
3.0 3.5 4.0 4.5 5.0 5.5 6.0 7.0 8.0 9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 Reeves Boom length Load (m) radius (m)
9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 Reeves
9.1 3.0m/73.8 68.7 64.4 55.4 45.9 39.2 34.1 27.0 22.3 19.0 9.2m/18.5
12.2 3.6m/66.9 63.1 55.4 45.8 39.1 34.0 26.9 22.2 18.9 16.3 11.9m/12.9
15.2
4.2m/58.4 53.3 45.8 39.0 33.9 26.8 22.1 18.7 16.2 12.7 10.3 14.5m/9.9
18.3
4.7m/47.4 44.0 39.0 33.9 26.8 22.1 18.7 16.2 12.6 10.3 8.6 17.1m/7.9
10
9
8
6
42.7m
45.7m
48.8m
51.8m
9.0m/16.5 14.7 11.8 9.4 7.7 6.5 5.5 4.7 4.1 3.5 3.1 2.6 2.3 2.0 1.7 1.4 38.3m/1.3
9.4m/15.0 14.2 11.5 9.4 7.7 6.4 5.4 4.7 4.0 3.5 3.0 2.6 2.2 1.9 1.6 1.3 1.1
10.0m/13.7 11.1 9.2 7.6 6.3 5.3 4.5 3.9 3.3 2.9 2.4 2.1 1.7 1.4 1.2
10.5m/12.6 10.8 8.9 7.5 6.2 5.2 4.4 3.8 3.2 2.7 2.3 1.9 1.6 1.3 1.1
3
2
2
2
21.3
5.2m/38.9 37.2 33.7 26.7 22.0 18.6 16.1 12.5 10.2 8.5 7.2 19.8m/6.3
5
24.4
5.7m/33.4 32.2 26.6 21.9 18.5 16.0 12.4 10.1 8.4 7.1 6.2 5.4 22.4m/5.3
5
Counterweight: 22.8 t Without Carbody Weight Crawler Fully Extended Unit: metric ton
27.4
6.3m/29.2 26.0 21.8 18.4 15.9 12.3 10.0 8.3 7.0 6.0 5.3 4.6 25.1m/4.3
6.8m/25.7 24.9 21.6 18.3 15.8 12.2 9.8 8.1 6.9 5.9 5.1 4.5 4.0 27.7m/3.5
4
4
Note: Ratings according to EN13000. Ratings shown in are determined by the strength of the boom or other structural components. Lifting capacities may vary depending on hook used or with/without auxiliary sheave. Please refer rated chart in operator’s cabin.
*0
30.5
33.5
36.6
7.3m/22.7 20.8 18.3 15.7 12.2 9.8 8.1 6.8 5.9 5.1 4.4 3.9 3.5 3.1 30.3m/3.0
7.9m/20.3 20.1 17.7 15.6 12.0 9.7 8.0 6.7 5.7 4.9 4.3 3.8 3.3 2.9 2.6 33.0m/2.3
3
3
39.6
8.4m/18.4 17.1 15.2 12.0 9.6 7.9 6.6 5.6 4.8 4.2 3.7 3.2 2.8 2.4 2.1 35.0m/1.9 3
Boom length (m) Load radius (m)
3.0 3.5 4.0 4.5 5.0 5.5 6.0 7.0 8.0 9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 Reeves Boom length (m) Load radius (m)
9.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 Reeves
27
TRANSPORTATION PLAN
Name
Weight (kg)
Dimension
Base Machine
11,470
· Boom base
· Wire rope
3,330
· Crawler
3,300
· Gantry
39,850
(Front / boom hoist) 3,500
Base Machine
8,210
· Gantry
(Front / rear / boom hoist)
3,300
· Wire rope
3,250
· Crawler
37,880
3,500
11,470
2,990
2,940
2,910
Base Machine · Boom base · Gantry · Wire rope (Front / rear / boom hoist) · Without crawler
2,990
3,500
7,700
3,500
2,940
2,990
2,870
Base Machine · Gantry · Wire rope (Front / rear / boom hoist) · Without crawler
25,490
23,520 2,890
Crawler 800 980
6,280
7,180
1,040
*1
30
PARTS AND ATTACHMENTS Backstop Weight: 245 kg
Base Machine Boom base, Gantry, Crawler, Wire rope (Front/boom hoist) Weight: 39,850 kg Width: 3,500 mm
4,650
11,470
620
3,300
Jib Tip Weight: 145 kg
3,330
670
3,400
620
Jib Base Weight: 125 kg
3,500 3,180
670
6.1 m Jib Insert Weight: 140 kg 620
Crawler Weight: 7,180 kg 800
6,280
670
980
6,160
1,040
500
Jib Strut Weight: 190 kg
840
3,620
650
640
930 1,050 640
640
1,370
Carbody Weight Weight: 3,270 kg / 1 piece
1,630
Counterweight No.4 (R) Weight: 2,740 kg
910
Counterweight No.4 (L) Weight: 1,660 kg
850
3,500
3,500
3,500
1,000
930
Counterweight No.3 Weight: 6,410 kg
930
Counterweight No.2 Weight: 7,860 kg
Counterweight No.1 Weight: 8,530 kg
+*
610
1,640
31
Auxiliary Sheave Weight: 150 kg
470
1,510
1,510
Boom Tip Weight: 1,110 kg
1,510
1,090
4,550
1,870
Boom Base Weight: 1,130 kg
5,350
1,120 1,490 Upper Spreader Weight: 280 kg
1,510
680
3.0 m Boom Insert Weight: 311 kg
3,160
1,490
300
1,580
6.1 m Boom Insert Weight: 522 kg
6,210
610
1,510
Lower Spreader Weight: 215 kg
1,490 870
280
Ball Hook Weight: 160 kg
390
300
1,490
330
590
1,510
9.1 m Boom Insert Weight: 742 kg
32 t Hook Weight: 500 kg
590
1,270 940
820
6,210
19 t Hook Weight: 400 kg
1,530 1,090
1,640
6.1 m Boom Insert With Lug Weight: 545 kg
1,490 80 t Hook Weight: 800 kg
50 t Hook Weight: 650 kg 9.1 m Boom Insert With Lug Weight: 765 kg
9,260
1,470 1,020
1,640
440
590
530
600
1,710 1,150
9,260
1,490
++
32
Note: This catalog may contain photographs of machines with specifications, attachments and optional equipment not certified for operation in your country. Please consult KOBELCO for those items you may require. Due to our policy of continual product improvements all designs and specifications are subject to change without advance notice. Copyright by KOBELCO CRANES CO., LTD. No part of this catalog may be reproduced in any manner without notice.
Inquiries To : 17-1, Higashigotanda 2-chome, Shinagawa-ku,Tokyo 141-8626 JAPAN Tel: +81-3-5789-2130 Fax: +81-3-5789-3372
URL: http://www.kobelco-cranes.com/
KOBELCO is the corporate mark used by Kobe Steel on a variety of products and in the names of a number of Kobe Steel Group companies.
Bulletin No. CKE800G-SPEC-EU2
120301F Printed in Japan
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Page 1 of 13
Date: 03 August 2016
PROJECT TITLE/ WO No:
Bedok Canal Improvement C1 Project
CLIENT:
PUB
LIFT PLAN TITLE:
ERSS Lifting Plan (7ton Vibro), Bedok Canal C1
LIFT CLASSIFICATION Please tick the appropriate box Standard Lift
Non Standard Lift
Critical Lift
< 39M
Circle radius = Working Boom Length + Load Protrusion NAME
PREPARED BY Yeu Wee Chek (Planning Engineer)
REVIEWED BY Islam Mohammed Amirul (Lifting Supervisor)
APPROVED BY Lim Seong San (Project Manager)
3 August 2016
3 August 2016
3 August 2016
SIGNATURE
DATE
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Lifting Zone
Lifting Zone
Crane Access
Page 2 of 13
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 3 of 13
Table of Contents 1.
Introduction ........................................................................................................................................................... 4
2.
Procedure ............................................................................................................................................................... 4
3.
Load Details (Calculation and Working Range) ........................................................................................... 6
4.
Rigging Method .................................................................................................................................................... 9
5.
Plot Plan ............................................................................................................................................................... 12
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 4 of 13
1. Introduction This document proposes the methods to be used for the Lifting Sheet pile This lifting plan covers only the lifting operations 1.1. Equipment KOLBECO CKE800G (80T) 1.2. Load Details 1.2.1. Sheet pile <1600 kg 1.2.2. Vibro Hammer < 8000kg 1.2.3. Lifting Hook 600kg+ Sheet pile 1600kg – Estimated Heaviest Load = 2200kg 2. Procedure Mobilization and Demobilization 1) Check and plan the travel routes prior mobilization of equipment to job site 2) Ensure travel routes and accesses to the job site are in good condition 3) Equipment to enter and occupy ERSS location to crane set up location 4) Banks-man to assist driver / crane operator in guiding for blind spots when safe moving of equipment 5) To set up the crane and position at ERSS location (as per plot plan) Preparation for lifting operation 1) Lifting supervisor to brief riggers, signalman and crane operators of the cranes lifting procedures for the Lifting Sheet pile, ERSS location shall coordinate with the site supervisor throughout the entire lifting operations 2) Barricades and displays warning signage within the crane working area 3) Riggers to check all lifting gears are in good condition and the correct sizes are used. Valid inspection for LM, LG, LA shall be in order 4) Crane operator to check the body, structures and devices of the crane component for any defects or malfunctions 5) Crane operator to ascertain the ground condition, weight of the load and lifting radius, and must also comply strictly in accordance with Lifting Checklist when setting up the crane 6) Signalman to check and ensue all cranes’ working area or load destination is free from obstacles or obstructions for safe moving before any lifting is to be carried out 7) Signalman and crane operator must have the common understanding in accordance with the standard signaling when lifting is carrying out. Radio communication or hand signal shall be used for the lifting operation 8) Lifting supervisor is responsible to ensure crane operator, riggers and signalman fully complied with all the crane lifting procedures throughout the entire lifting operations 9) Lifting gears to be used as follows;
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 5 of 13
a. 1nos x 8m Lifting Chain b. 1no x 12ton shackle c. 1no x 2m xx20mm Wire roap both end eye
Lifting procedure 1) To set up 80 tons crane and position at ERSS location (as per plot plan) 2) Attached all lifting gears crane hook block, swing and lower down the crane boom until crane hook block top of the location and stop. 3) Rigs and secured lifting gears onto the load. 4) Used 2 tag line to control and minimize load movement 5) Lifting supervisor and crane operator shall counter check on the crane stability when the crane has totally taken off the load 6) When load is clear from any obstruction crane boom slowly hoist up and swing from initial position west to north by anti-clockwise direction as attached plot plan 7) Slowly lower the load onto the ground 8) Remove lifting gears 9) Demobilize the crane and perform proper housekeeping
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
3. Load Details (Calculation and Working Range) Load Data Calculations Heaviest Load
Lifting Material Adding 10% of the load Hook block weight Total Load Boom Length Working Radius Safe Working Load Safety Factor Crane capacity use
: 1600 kg (Heaviest) : 1760 kg : 600 kg (inclusive of lifting gears) + 8000kg (Vibro Hammer) : 10,360 kg : 33.5 M :8M : 26,400 kg : 26,400 kg / 10,360 kg = 2.55 : 10,360 kg / 26,400 kg % = 39.24%
Page 6 of 13
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 7 of 13
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 8 of 13
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 9 of 13
4. Rigging Method
10T webbing sling w/ protected eye
Vi 10T webbing sling w/ protected eye
12T shackle pin
V
< 39M
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 10 of 13
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 11 of 13
JOB No.
DOC No.
REV.0
10-0115P025-LP-008
Lifting Plan
Date: 03 August 2016
Page 12 of 13
5. Plot Plan
360°swing radius with 21m working radius
C B A A → Pick up point Radius= 21m B → Drop off point Radius= 21m C → Swing Radius jhnte’hRadius= 21m (max) Boom Length= 39m
B
C A
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
Page 1 of 10
Date: 22 Aug 2016
PROJECT TITLE/ WO No:
Bedok Canal Improvement C1 Project
CLIENT:
PUB
LIFT PLAN TITLE:
Lifting Sheet Pile by Vibro Mounted Excavator, Bedok Canal C1
LIFT CLASSIFICATION Please tick √ the appropriate box Standard Lift
Non Standard Lift
Critical Lift Lifting in this area is “Near”
Centre of Rotation
Circle radius = Working Boom Length + Load Protrusion NAME
PREPARED BY Yeu Wee Chek (Planning Engineer)
REVIEWED BY Islam Mohammed Amirul (Lifting Supervisor)
APPROVED BY Lim Seong San (Project Manager)
22 Aug 2016
22 Aug 2016
22 Aug 2016
SIGNATURE
DATE
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
Date: 22 Aug 2016
Lifting Zone
Lifting Zone
Page 2 of 10
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
Date: 22 Aug 2016
Page 3 of 10
Table of Contents 1.
Introduction ................................................................................................................................. 4
2.
Procedure ..................................................................................................................................... 4
3.
Load Details(Calculation and working range) .................................................................... 6
4.
Rigging Plan ................................................................................................................................ 8
5.
Plot Plan ....................................................................................................................................... 9
6.
Ground Bearing….…………………………….…………………………………………………………..……………………..11
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
Date: 22 Aug 2016
Page 4 of 10
1. Introduction • This document proposes the methods to be used for the Lifting “H-beam for fitting” • This lifting plan covers only the lifting operations 1.1. Equipment KOLBECO SK480LC-8 1.2. Load Details 1.2.1. 14m sheet pile 1600kg - Estimated Heaviest Load 2. Procedure Mobilization and Demobilization 1) Check and plan the travel routes prior mobilization of equipment to job site. 2) Ensure travel routes and accesses to the job site are in good condition 3) Equipment to enter and occupy proposed sheetpile location. 4) Banks-man to assist driver / vibro-mounted excavator operator in guiding for blind spots when safe moving of equipment 5) Position at proposed sheetpile location (as per plot plan) Preparation for lifting operation 1) Lifting supervisor to brief riggers, signalman and vibro-mounted excavator operators of the vibro-mounted excavators lifting procedures for the Lifting sheet pile at proposed location, lifting supervisor shall coordinate with the site supervisor throughout the entire lifting operations 2) Barricades and displays warning signage within the vibro-mounted excavator working area. 3) Riggers to check all lifting gears are in good condition and the correct sizes are used. Valid inspection for LM, LG, LA shall be in order 4) vibro-mounted excavator operator to check the body, structures and devices of the vibromounted excavator component for any defects or malfunctions 5) vibro-mounted excavator operator to ascertain the ground condition, weight of the load and lifting radius, and must also comply strictly in accordance with Lifting Checklist when setting up the crane 6) Signalman to check and ensue all vibro-mounted excavators’ working area or load destination is free from obstacles or obstructions for safe moving before any lifting is to be carried out 7) Signalman and vibro-mounted excavator operator must have the common understanding in accordance with the standard signaling when lifting is carrying out. Radio communication or hand signal shall be used for the lifting operation 8) Lifting supervisor is responsible to ensure vibro-mounted excavator operator, riggers and signalman fully complied with all the vibro-mounted excavator lifting procedures throughout the entire lifting operations
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
Date: 22 Aug 2016
Page 5 of 10
9) Lifting gears to be used as follows; a. 8nos x 12ton x Bon Screw Pin Shackle b. 12nos x 10ton x Polyester Webbing Sling w/ Protected Eyes Lifting procedure 1) To set up vibro-mounted excavator and position at proposed sheetpile location. (as per plot plan) 2) Attached all lifting gears vibro-mounted excavator hook, swing and lower down the vibromounted excavator boom until vibro-mounted excavator hook top of the location and stop. 3) Rigs and secured lifting gears onto the load. 4) Additional safe line and shackle will be hooked to I-beam pinhole as the additional safety measure to prevent object fall on site workers. 5) Used 1 tag line to control and minimize load movement 6) Lifting supervisor and vibro-mounted excavator operator shall counter check on the vibromounted excavator stability when the vibro-mounted excavator has totally taken off the load 7) When load is clear from any obstruction vibro-mounted excavator boom slowly hoist up and swing from initial position west to north by anti-clockwise direction as attached plot plan. 8) Slowly lower the load onto driven sheetpile. 9) Remove lifting gears 10) Respected do the above the Demobilize the crane and perform proper housekeeping
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan 3. Load Details (Calculation and Working Range) Load Data Calculations Est. Heaviest Load Lifting Material Adding 10% of the load Lifting Gear Weight Total Load Boom Length Working Radius Safe Working Load Safety Factor Crane capacity use
: 1600 kg (Est. Heaviest Load) : 1760 kg : 200 kg : 1960 kg ~2000kg : 18.58 M (Maximum) : 5.0 M : 6000 kg : 6000 kg / 2000 kg = 3.0 : 2000 kg / 6000 kg % = 33.3%
Date: 22 Aug 2016
Page 6 of 10
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
Date: 22 Aug 2016
Page 7 of 10
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
Date: 22 Aug 2016
Page 8 of 10
4. Rigging Method
Double Wrap of 10T Webbing Sling
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
Date: 22 Aug 2016
Page 9 of 10
12T shackle
360°swing radius with 5m working radius
JOB No.
DOC No.
REV.1
10-0115P025-LP-024
Lifting Plan
5.
Date: 22 Aug 2016
Page 10 of 10
Plot Plan
360°swing radius with 5m working radius
B
Lifting Zone C A
(A)→ Pick up point Radius= 5m (B)→ Drop off point Radius= 5m (C)→ Swing Radius Radius= 5m (max) Boom Length= 18.58m
Lifting Zone A C
B
HYDRAULIC E
VIBRATORY
PIIB
DRIVBR m.m,
D I MENS IONS MODEL
PCF250 PCF3OO PCF35O PCF450
-.
ITEM
*U
f;U
2350
2600
*U +
f;U
50
-.
+
A
1
800
21
B
1
250
1
400
1
570
650
1
c
850
1
050
1
100
120
D
950
1
100
1
300
140
E
215
215
215
215
F
600
710
730
910
G
250
280
300
350
H
350
430
450
500
I
50
50
50
50
J
1420
1
790
1
2050
860
SPECIFICAT IONS PCF 250
PCF 300
PCF 350
PCF 450
fi|J
*|J
f;U
fiU
3000
3200
3500
3500
500
2200
2800
3500
kg /cm'
280
320
325
350
TONS
20.5
35,6
45
60
m
9
13
16
18
TONS
1B-25
30-40
40-50
40-65
4
FREOUENCY kg
WEIGHT
OPFRATING PRESSURE VIBRATORY FORCE
MAX PILE
LENGTH
SUITABLE CARRIER
1
+
+
+
SK460-8
ACERA GEOSPEC SK460-8/SK480LC-8
SK480LC-8
STANDARD EQUIPMENT ENGINE ■ Engine, HINO P11C, Diesel engine with turbocharger and intercooler ■ Automatic engine deceleration ■ Auto Idle Stop (AIS) ■ Batteries (2 x 12V - 60Ah) ■ Starting motor (24V - 6 kW), 60 amp alternator ■ Removable clean-out screen for radiator ■ Automatic engine shut-down for low engine oil pressure ■ Engine oil pan drain cock ■ Double element air cleaner CONTROL ■ Working mode selector (H-mode and S-mode) ■ Power Boost SWING SYSTEM & TRAVEL SYSTEM ■ Swing rebound prevention system ■ Straight propel system ■ Two-speed travel with automatic shift down ■ Sealed & lubricated track links ■ Grease-type track adjusters ■ Automatic swing brake HYDRAULIC ■ Arm regeneration system ■ Auto warm up system ■ Aluminum hydraulic oil cooler MIRRORS & LIGHTS ■ Two rearview mirrors ■ Three front working lights ■ Swing flashers
CAB & CONTROL ■ Two control levers, pilot-operated ■ Tow eyes ■ Horn, electric ■ Integrated left-right slide-type control box ■ Ashtray ■ Cigarette lighter ■ Cab light (interior) ■ Coat hook ■ Luggage tray ■ Large cup holder ■ Detachable two-piece floor mat ■ 7-way adjustable suspension seat ■ Retractable seatbelt ■ Headrest ■ Handrails ■ Heater and defroster ■ Intermittent windshield wiper with double-spray washer ■ Skylight ■ Tinted safety glass ■ Pull-type front window and removable lower front window ■ Easy-to-read multi-display monitor ■ Automatic air conditioner ■ Emergency escape hammer ■ Suspension seat
OPTIONAL EQUIPMENT ■ Wide range of buckets ■ Various optional arms ■ Wide range of shoes ■ Front-guard protective structures (May interfere with bucket action)
■ Additional track guide ■ Additional hydraulic circuit ■ Rain visor ■ Multi-control valve
Hydraulic Excavators
■ Bucket Capacity:
1.35 – 3.4 m3 ISO heaped ■ Engine Power:
257kW {350 PS}/1,850 min-1{rpm} (ISO14396)
■ Operating Weight (800 mm shoe):
■ Heavy-Duty Application for Quarry • Full
undercover to reinforce main carriage A 6 mm steel undercover covers the entire bottom surface of the upper frame, protecting the engine, pumps and other components from rock fragments, boulders, iron bar, and other debris.
• Lower
undercover A 9 mm steel cover protects the lower frame from rocks, steel bar, and other materials that could damage hydraulic piping and other components.
• Heavy-duty
track shoes for rock crushing Heavy-duty track shoes are thicker and the lugs are higher to provide even more protection against breakage and loss.
• More
track guides Four durable track guides are fitted on each side to prevent wheel dislocation and protect the rollers. Attached with bolts, they are easy to install and remove.
Note: Standard and optional equipment may vary. Consult your KOBELCO dealer for specifics.
Note: This catalog may contain attachments and optional equipment that are not available in your area. And it may contain photographs of machines with specifications that differ from those of machines sold in your areas. Please consult your nearest KOBELCO distributor for those items you require. Due to our policy of continuous product improvements all designs and specifications are subject to change without advance notice. Copyright by No part of this catalog may be reproduced in any manner without notice. Inquiries To: 17-1, Higashigotanda 2-chome, Shinagawa-ku, Tokyo 141-8626 JAPAN Tel: +81 (0) 3-5789-2146 Fax: +81 (0) 3-5789-2135 www.kobelco-kenki.co.jp/english_index.html
Bulletin No. ACERA GEOSPEC SUPER SK460/SK480LC-SEASIA-HS-201 2012021000 Printed in Japan
47,800 kg – SK460 48,800 kg – SK480LC
Announcing ACERA GEOSPEC and the Concept of Beautiful Performance.
The Power Wave of Change
When we set out to design our new hydraulic excavators, we kept our eyes on the big picture. Of course we wanted machines with greater digging capacity. But they also had to be fuel-efficient and economical, while imposing less of a burden on the local and global environments. Applying our advanced technologies, we developed KOBELCO’s new ACERA GEOSPEC series, an entirely new kind of excavator that beautifully balances all the demands of today’s construction industry. Lean and efficient with capacity to spare, these sleek powerhouses bring a whole new style to the worksite while setting new standards for environmental responsibility.
Pursuing the “Three E’s”
The Perfection of Next-Generation, Network Performance Enhancement
Greater Performance Capacity
New hydraulic circuitry minimizes pressure loss High-efficiency, electronically controlled Common Rail Fuel Injection Engine Powerful travel and arm/bucket digging force
Economy
Improved Cost Efficiency
Advanced power plant that reduces fuel consumption Easy maintenance that reduces upkeep costs High structural durability and reliability that retain machine value longer
Environment
Features That Go Easy on the Earth
Auto Idle Stop as standard equipment Noise reduction measures (with improvement of the sound quality) minimize noise and vibration
ACERA GEOSPEC The “GEO” in GEOSPEC expresses our deep respect for our planet, and for the solid ground where excavators are in their element. This is accompanied by SPEC, which refers to the performance specifications needed to get the job done efficiently as we carry on the tradition of the urban-friendly ACERA series.
1
Photos in this catalog are the optional specs with 0.93 m3 bucket, 800 mm shoes, arm rock guard, and pre-air cleaner.
2
Performance
The GEOSPEC Difference:
NEXT-3E Technology Next-Generation Electronic Engine Control
Efficient Performance!
The high-pressure, common-rail fuel-injection engine features adjustable control to maximize fuel efficiency and provide powerful medium/low-speed torque. The result is a highly fuel-efficient engine.
Amazing Productivity with a 18 % Increase in Work Volume and “Top-Class” Cost-Performance
H
For heavy duty when a higher H-Mode performance level is required.
Work Volume*
18 %
S
increase in work volume using the same amount of fuel. (H-Mode)
S-Mode
decrease in fuel consumption even when performing more work volume. (S-Mode)
Optional Attachment Mode Selector Switch There’s a choice of three different hydraulic circuits, to accommodate bucket, crusher or breaker, and the desired attachment mode can be selected with a switch, which automatically configures the selector valve. All attachment modes can be used in either S-mode or H-mode.
“Top-Class” Powerful Digging Max. arm crowding force: Max. arm crowding force with power boost: Max. bucket digging force: Max. bucket digging force with power boost:
For normal operations with lower fuel consumption.
Optional N&B (crusher and breaker) The operator selects the desired mode from inside the cab, and the selector valve automatically configures the machine accordingly.
Fuel Consumption*
18 %
Simple Select: Two Digging Modes
203 kN {20.7 tf} 222 kN {22.7 tf} 267 kN {27.2 tf} 292 kN {29.8 tf}
Powerful Travel Travel torque: increased by Drawbar pulling force:
4% 417 kN {42.5 tf}
Seamless, Smooth Combined Operations The GEOSPEC machines have inherited the various systems that make inching and combined operations easy and accurate, with further refinements that make a good thing even better. Leveling and other combined operations can be carried out with graceful ease.
Greater Swing Power, Shorter Cycle Times Swing torque: increased by Swing speed:
8.8 % 7.8 min-1
● Electronic Active Control System ● Arm regeneration system ● Boom lowering system ● Variable swing priority system ● Swing rebound prevention system
Significant Extension of Continuous Working Hours The combination of a large-capacity fuel tank and excellent fuel efficiency delivers an impressive 34 % increase in continuous operation hours.**
Fuel tank:
650L
34 %
Light Lever Operation It takes 10% less effort to move the control levers, so that operators can work longer hours with less fatigue.
10 % Less
NEXT-3E Technology New Hydraulic System Rigorous inspections for pressure loss are performed on all components of the hydraulic piping, from the first spool of the control valve to the connectors. This regimen, combined with the use of a new, high-efficiency pump, cuts energy loss to a minimum.
*The value shows results from actual measurements taken by KOBELCO when compared with previous KOBELCO models. **The value shows results from actual measurements taken by KOBELCO for continuous operation in S Mode, compared with previous models. Results vary depending on the method of operation and load conditions.
3
NEXT-3E Technology Total Tuning Through Advanced ITCS Control The next-generation engine control is governed by a new version of ITCS, which responds quickly to sudden changes in hydraulic load to ensure that the engine runs as efficiently as possible with a minimum of wasted output. ITCS (Intelligent Total Control System) is an advanced, computerized system that provides comprehensive control of all machine functions.
4
Reliability, Durability, Environmental Responsibility
The GEOSPEC Difference:
The Value and Quality of Sturdy Construction! Stable Attachment Strength
The GEOSPEC Difference: Designed for the Environment and the Future!
Emergency Acceleration (Dial) Permits Continued Operation in the Unlikely Event of Malfunction
Forged and cast components are used throughout. The standard arm and boom also meet specifications that were classified as “reinforced” on previous KOBELCO models to ensure reliable strength.
If unexpected trouble is experienced with the ITCS mechatronic control system, the machine can still be operated using the emergency acceleration system. Digging modes are also automatically relayed to an emergency system so that digging can continue temporarily until a service person arrives to repair the primary system.
HD boom
Auto Idle Stop Provided as Standard Equipment
Engine throttle Mechatronic controller
Engine
Pre-air Cleaner (optional)
Pump Engine ECU
The optional pre-air cleaner prolongs a replacement cycle of main air cleaner.
Emergency acceleration
Newly designed MCU ● Vertical
HD arm New MCU
Conventional MCU
Countermeasures Against Electrical System Failure All elements of the electrical system, including controller, have been designed for enhanced reliability.
Automatic Acceleration/Deceleration Function Reduces Engine Speed Engine speed is automatically reduced when the control lever is placed in neutral, effectively saving fuel and reducing noise and exhaust emissions. The engine quickly returns to full speed when the lever is moved out of neutral.
Engine Speed
alignment and sealed cover gives better protection from water and dust ● Integration in base plate boosts assembly quality ● Reliable fixture to base plate
This function saves fuel and cuts emissions by shutting down the engine automatically when the machine is on stand by. It also stops the hourmeter, which helps to retain the machine’s asset value.
Lever Off (Neutral)
Lever On Lever Stroke
Low Noise Level and Mild Sound Quality HD bucket (optional)
The electronically controlled common-rail engine has a unique fuel injection system that runs quietly. Also, the hydraulic pumps have been redesigned to produce a more pleasant sound during pressure relief. In short, the GEOSPEC series meets all requirements cited in latest EU stage II.
Meets EMC (Electromagnetic Compatibility) Standards in Europe. Measures have been taken to ensure that the GEOSPEC machines do not cause electro-magnetic interference.
Enhanced Upper Carbody Strength The structure of the lower portion of the upper frame has been reassessed and the undercover area has been minimized for further strength.
5
Durability That Retains Machine Value Five and T Ten Years in the Future ●New operator’s seat covered in durable, material ●High-quality urethane paint ●Easily repaired bolted hand rails
6
Maintenance
The GEOSPEC Difference:
“On the Ground” Maintenance! Highly Durable Super-fine Filter Comfortable "On the Ground" Maintenance
Access through the
1
All of the components that require regular maintenance are laid out for easy access, with the control valves located on a single right-hand that opens and closes at a touch. Behind that, in the pump compartment, there is remote access to such components as the engine oil filter and fuel filter (with built-in water separator). On the left side are the intercooler, air cleaner, radiator coolant, etc. Daily maintenance can be carried out easily without the need to climb up onto the machine.
left side cover
The high-capacity hydraulic oil filter incorporates glass fiber with superior cleaning power and durability. With a replacement cycle of 1,000 hours and a construction that allows replacement of the filter element only, it’s both highly effective and highly economical.
The fuel filter with built-in water separator functions in two ways by removing large contaminants and separating out water. ● Super-fine filter
Double-Element Air Cleaner as Standard 3 4 5 6 Engine oil filter
Access through the
The large-capacity element features a double-filter structure that keeps the engine running clean even in dusty environments.
Two large fuel filters (built-in water separator)
Air cleaner (double element)
right side cover
High-Grade Fuel Filter with Superior Filtration Performance
Radiator and oil cooler are aligned side by side, with intercooler positioned in front. This more effective layout gives outstanding cooling results.
The high-performance, large capacity filter is designed specially for the common-rail fuel-injection engine.
2 7
Monitor Display with Essential Information for Accurate Maintenance Checks ●Displays only the maintenance information that’s needed, when it’s needed. ●Self-diagnostic function that provides earlywarning detection and display of electrical system malfunctions. ●Record previous breakdowns, including irregular and transient malfunctions.
8 Intercooler
Air cleaner
Fuel cooler
Quick Oil Drain Valves for Quick Maintenance 1
A quick drain valve, which requires no tools, is provided as standard equipment.
Choice of 16 Languages for Monitor Display With messages including those requiring urgent action displayed in the local language, s in all parts of the world can work with greater peace of mind.
Quick drain valve
2
To facilitate fuel tank cleaning, the fuel drain valve was made larger and fitted with a flange on the bottom. Chinese
German
English
English (US)
French
Indonesian
ISO
Italian
Japanese
Malay
Myanmar(Brumese) Portuguese
Spanish
Tamil
Thai
Fuel drain valve
More Efficient Maintenance Inside the Cab Drain Detachable type
3
● Detachable two-
piece floor mat with handles for easy removal. A floor drain is located under the mat.
7
4
● Easy-access fuse
box. More finely differentiated fuses make it easier to locate malfunctions.
5
6
● Air conditioner filter
● Hour meter can be
can be easily removed without tools for cleaning.
checked while standing on the ground.
7
● Large-capacity tool
box can hold up to three pails.
8
● Special crawler frame
Vietnamese
design is easily cleaned of mud
8
Comfort and Safety
The GEOSPEC Difference:
Newly Designed Information Display Prioritizes Visual Recognition
Designed from the Operator’s Point of View
The analog gauge provides information that’s easy to read regardless of the operating environment. The information display screen has been enlarged, and a visor is attached to further enhance visibility.
Wide Field of View Liberates the Operator
The GEOSPEC Difference: Imagining Possible Scenarios and Preparing in Advance Bracket for Attaching a Head Guard Provided as Standard Equipment
The front field of view easily clears ISO standards, while the peripheral view reduces blind spots to a minimum.
A bracket is provided as standard equipment that allows the optional head guard to be simply bolted on.
Safety Features That Take Various Scenarios into Consideration
● Firewall separates the pump
● Hammer for emergency exit
compartment from the engine
●A long wiper covers a wide area for a broad view in bad weather. ●Back mirrors provide a safe view of the rear. ●Reinforced green glass windows meet European standards.
Wide-Access Cab Ensures Smooth Entry and Exit
+35mm
The left control box lifts up with the safety lock lever to add 10° to the cab entry angle for easy entrance and exit.
● Swing
flashers/rear working
lights ● Thermal guard prevents with hot components during engine
inspections ● Hand rails meet European standards ● Retractable seatbelt requires no manual adjustment
10° Photo includes optional pedals for N&B and rotation.
Plenty of Foot Room
Creating a Comfortable Operating Environment
With a total width of 1,005 mm, the cab has 35 mm more frontto-back foot room than previous models. The travel pedal is larger for greater operator comfort.
Reduced Vibration for Fatigue-Free Operation automatic air ● Spacious luggage tray conditioner
● Double slide and suspen- ● Powerful
The rigid cab construction and liquid-filled viscous cab mounts minimize cab vibration. In addition, the use of new lower rollers on the crawlers cuts travel vibration in half compared with previous models.
sion seat
● New interior design and
materials create an elegant feel
In-Cab Noise is Reduced by 4dB Compared with Previous Models. ●Seat can be reclined to horizontal position
9
● One-touch lock release ● Large cup holder
simplifies opening and closing the front window
10
Specifications
SK460-8
Engine
Travel System
SK480LC-8
Working Ranges Unit: m
Travel motors: Travel brakes: Parking brakes:
HINO P11C Direct injection, water-cooled, 4-cycle diesel engine with turbocharger, intercooler
Model Type No. of cylinders: Bore and stroke: Displacement:
6 122 mm X 150 mm 10.520 L 257 kW {350 PS}/1,850 min-1 {rpm} (ISO14396: 2002) 243 kW {333 PS}/1,850 min-1 {rpm} (ISO9249: 2007)* 1,400 N•m/1,400 min-1 {rpm} (ISO14396:2002) 1,359 N•m/1,400 min-1 {rpm} (ISO9249:2007)*
Rated power output: Max. torque:
2 X axial-piston, two-step motors Hydraulic brake per motor Oil disc brake per motor 47 each side (SK460) 50 each side (SK480LC) 5.4/3.4 km/h 417 kN {42.5 tf} (ISO 7464) 70 % {35°} 510 mm
Travel shoes: Travel speed: Drawbar pulling force: Gradeability: Ground clearance:
Arm Range a - Max. digging reach
Cab & Control
Two variable displacement pumps + 1 gear pump 2 X 370 L/min, 1 X 30 L/min
Type: Max. discharge flow: Relief valve setting Boom, arm and bucket: Power Boost: Travel circuit: Swing circuit: Control circuit: Pilot control pump: Main control valves: Oil cooler:
31.4 MPa {320 kgf/cm2} 34.3 MPa {350 kgf/cm2} 34.3 MPa {350 kgf/cm2} 25.0 MPa {255 kgf/cm2} 5.0 MPa {50 kgf/cm2} Gear type 6-spool Air cooled type
Brake: Parking brake: Swing speed: Tail swing radius: Min. front swing radius:
Standard 3.45 m
Long 4.9 m
12.07
13.48
10.63
11.54
11.84
13.28
cdef-
6.48 10.49 6.91 3.11
7.36 11.16 7.72 3.22
7.81 10.93 7.58 2.77
9.26 11.70 8.29 1.32
4.00
6.68
7.12
8.41
4.75
5.27
5.14
5.30
3.59
5.21
6.1
8.28
6.31
7.21
7.67
9.15
3.4
2.1
1.9
1.35
Max. digging depth Max. digging height Max. dumping clearance Min. dumping clearance
j - Digging depth for 2.4 m (8') flat bottom Bucket capacity ISO heaped m3
Digging Force (ISO 6015)
b h
d e
f i
Unit: kN (tf)
Arm length Bucket digging force
ME Short 2.4 m 3.0 m 279 {28.0} 266 {27.1} 305 {31.1}* 291 {29.7}*
Standard 3.45 m 267 {27.2} 292 {29.8}*
Long 4.9 m 263 {26.8} 288 {29.4}*
247 {25.2} 223 {22.8} 270 {27.5}* 244 {24.9}*
203 {20.7} 222 {22.7}*
157 {16.0} 172 {17.6}*
c
j
g
*Power Boost engaged.
13m 12 11 10 9 8 7 6 5 4 3 2 1
12 m 11 10 9 8 7 6 5 4 3 2 1 0 1 2 3 4 5 6 7 8m
Standard Arm
Boom cylinders: Arm cylinder: Bucket cylinder:
Swing System Swing motor:
Short 3.0 m 11.77
Arm crowding force
Boom, Arm & Bucket
ME 2.4 m 10.88
i - Horizontal digging stroke at ground level
Cab All-weather, sound-suppressed steel cab mounted on the silicon-sealed viscous mounts and equipped with a heavy, insulated floor mat. Control Two hand levers and two foot pedals for travel Two hand levers for excavating and swing Electric rotary-type engine throttle
Pump
a
7.0 m
b - Max. digging reach at ground level
g - Max. vertical wall digging depth h - Min. swing radius
*Previous indication
Hydraulic System
6.3 m
Boom
170 mm X 1,590 mm 190 mm X 1,970 mm 160 mm X 1,410 mm
Dimensions
Refilling Capacities & Lubrications
Axial-piston motor Hydraulic; locking automatically when the swing control lever is in the neutral position Hydraulic disc brake 7.8 min-1 {rpm} 3,670 mm 5,140 mm
Fuel tank: Cooling system: Engine oil: Travel reduction gear: Swing reduction gear:
650 L 41 L 50 L 2 X 15 L 2X7L
Hydraulic oil tank:
555 L tank oil level 300 L hydraulic system
Arm length
ME 2.4 m
Short 3.0 m
Standard 3.45 m
Long 4.9 m
A Overall length
11,620
12,080
12,030
12,090
4,260
3,800
3,570
4,410
B
Overall height (to top of boom)
SK460 SK480LC D Overall height (to top of cab) E Ground clearance of rear end* F Ground clearance* C Overall width
3,310 1,340 510
3,550 (with 800 mm shoes) 3,550 (with 800 mm shoes) 3,310 3,310 1,340 1,340 510 510
G Tail swing radius G’
Distance from center of swing to rear end
H Tumbler distance I
Overall length of crawler
SK460 SK480LC SK460 SK480LC
J Track gauge K Shoe width L Overall width of upperstructure
3,310 1,340 510
3,670
3,670
3,670
Unit: mm 3,670
3,670
3,670
3,670
3,670
4,060 4,400 5,110 5,450 2,750
4,060 4,060 4,400 4,400 5,110 5,110 5,450 5,450 2,750 2,750 600/800/900 3,000 3,000
4,060 4,400 5,110 5,450 2,750
3,000
3,000
* Without including height of shoe lug.
A L
G, G’
Attachments B
Backhoe bucket and arm combination
D
Backhoe bucket Normal digging
Wide
E
Mass excavating
Heavy digging
Use
F K
H
J
I Bucket capacity Opening width No. of bucket teeth Bucket weight
11
ISO heaped Struck With side cutter Without side cutter
m3 m3 mm mm kg
1.35 1.0 1,225 1,100 4 1,250 —
2.4 m ME arm * 3.0 m short arm ○ Combinations 3.45 m STD arm ○ 4.9 m long arm ◎ ◎ Recommended ○ Loading only △ Not recommended
1.6 1.15 1,375 1,250 4 1,330 —
1.9 1.4 1,670 1,550 5 1,510 —
○
○
2.1 1.5 1,750 1,630 5 1,560 —
2.4 1.7 1,980 1,860 5 1,690 —
1.9 1.4 1,590 1,510 4 2,150 —
2.1 1.5 1,660 1,580 5 2,270 —
◎
△
○
○
◎
△
—
—
— — — △ △ *ME arm specs should be used for light-digging.
◎
◎
△
3.4 2.5 1,990 1,870 6 2,190 ◎* — — —
C
Operating Weight & Ground Pressure In standard trim, with standard boom, 3.45 m arm, and 1.9 m3 ISO heaped bucket Shaped Shoe width
mm
Overall width
mm
Ground pressure
kPa (kgf/cm2)
Operating weight
kg
SK460 SK480LC SK460 SK480LC SK460 SK480LC
600 3,350 3,350 86 {0.87} 81 {0.83} 46,400 47,300
Triple gro shoes (even height) 800 3,550 3,550 66 {0.67} 63 {0.64} 47,800 48,800
900 3,650 3,650 59 {0.61} 56 {0.58} 48,300 49,400
12
Lifting Capacities
SK460-8
A - Reach from swing centerline to bucket hook B - Bucket hook height above/below ground C - Lifting capacities in kilograms • Max. discharge pressure: 34.3 MPa (350 kgf/cm2)
Rating over front
Rating over side or 360 degrees
SK460
Standard Arm: 3.45 m Bucket: 1.9 m ISO heaped 1,510 kg Shoe: 600 mm 1.5 m 3.0 m 4.5 m 6.0 m 3
A
7.5 m
9.0 m
10.5 m
At Max. Reach Radius
B 7.5 m 6.0 m 4.5 m 3.0 m 1.5 m G. L. -1.5 m -3.0 m -4.5 m -6.0 m
kg kg kg kg kg kg kg kg kg kg
SK460
*7,930 *7,930 *9,740 *9,740 *13,390 *13,390 *15,010 *15,010 *19,640 *19,640 *26,610 *26,610
*8,750 *17,500 *17,500 *12,400 12,250 *9,930 *20,650 17,430 *14,260 11,350 *11,050 *20,810 16,710 *15,480 10,780 *11,890 *22,070 16,530 *15,950 10,510 11,960 *21,100 16,650 *15,610 10,500 11,930 *18,970 17,040 *14,260 10,720 *10,890 *15,020 *15,020 *11,120 *11,120
Short Arm: 3.0 m Bucket: 2.1 m ISO heaped 1,560 kg Shoe: 600 mm 3.0 m 4.5 m 6.0 m
*8,750 8,610 8,090 7,710 7,500 7,480 7,670
*7,160 *7,350 *7,870 *8,540 *9,200 9,170 9,040 9,070
7,060 6,930 6,660 6,340 6,040 5,800 5,680 5,710
*7,350 7,310
*6,550 *6,550 *6,550 5,740 *6,750 5,100 4,770 *7,150 4,750 4,610 7,290 4,600 7,430 4,670 7,930 4,980 8,970 5,650 *9,800 7,020 *10,250 *10,250
9.16 m 9.87 m 10.31 m 10.52 m 10.51 m 10.28 m 9.81 m 9.07 m 7.98 m 6.35 m
3
A
7.5 m
9.0 m
At Max. Reach Radius
B 9.0 m 7.5 m 6.0 m 4.5 m 3.0 m 1.5 m G. L. -1.5 m -3.0 m -4.5 m -6.0 m
kg kg kg kg kg kg kg kg kg kg kg
SK460
*12,410 *20,100 *24,550
*12,410 *20,100 *24,550
*18,790 *15,970 *17,860 *21,900 *20,570 *18,030 *13,310
18,510 *15,970 16,680 16,640 16,850 17,320 *13,310
*11,060 *13,090 *14,790 *15,800 *16,030 *15,420 *13,690
*11,060 12,040 11,230 10,750 10,560 10,620 10,920
Long Arm: 4.9 m Bucket: 1.35 m ISO heaped 1,250 kg Shoe: 600 mm 1.5 m 3.0 m 4.5 m 6.0 m
*8,330 *9,290 *10,410 *11,430 *12,150 12,020 *11,950 *10,240
*8,330 9,070 8,520 8,050 7,710 7,560 7,590 7,880
*7,850 *8,300 *8,910 9,410 9,200 9,110
6,840 6,600 6,300 6,030 5,830 5,760
*7,930 *7,720 *7,630 *7,790 7,730 7,600 7,780 8,350 9,540 *9,880 *9,660
*7,930 7,110 5,980 5,310 4,950 4,820 4,910 5,280 6,060 7,670 *9,660
7.79 m 8.88 m 9.61 m 10.06 m 10.28 m 10.27 m 10.03 m 9.55 m 8.79 m 7.65 m 5.93 m
3
A
7.5 m
9.0 m
10.5 m
At Max. Reach Radius
B 9.0 m 7.5 m 6.0 m 4.5 m 3.0 m 1.5 m G. L. -1.5 m -3.0 m -4.5 m -6.0 m
kg kg kg kg kg kg kg kg kg kg kg kg
-7.5 m
SK460
*3,640 *3,640 *6,960 *6,960 *10,550 *10,550 *14,680 *14,680 *19,780 *19,780
*9,110 *8,730 *11,260 *15,020 *20,000 *26,960
*9,110 *8,730 *11,260 *15,020 *20,000 *26,960
*17,110 *17,110 *12,070 *19,960 16,960 *13,890 *21,360 16,210 *15,050 *21,580 15,970 *15,490 *20,710 16,070 *15,130 *18,550 16,490 *13,730
11,820 10,910 10,340 10,080 10,080 10,320
*8,180 *9,520 *10,680 *11,520 11,580 11,570 *10,430
*8,180 8,290 7,730 7,340 7,130 7,120 7,330
*6,400 *7,190 *8,030 *8,780 8,850 8,710 8,740
*6,400 6,510 6,100 5,740 5,490 5,360 5,380
*5,070 *5,770 *6,110 *6,570 *7,090 7,080 6,920 6,880
*5,070 5,290 5,090 4,850 4,600 4,380 4,230 4,190
*20,380 *20,380 *14,390 *14,390 *10,450 *10,450
ME Arm: 2.4 m Bucket: 3.4 m ISO heaped 2,190 kg Shoe: 600 mm 3.0 m 4.5 m 6.0 m
*4,390 *4,200 *4,150 *4,210 *4,380 *4,670 *5,130 *5,820 6,670 7,700 *8,430
*4,390 *4,200 *4,150 3,920 3,650 3,530 3,540 3,700 4,060 4,740 6,060
9.92 m 10.80 m 11.40 m 11.79 m 11.97 m 11.96 m 11.76 m 11.35 m 10.72 m 9.82 m 8.55 m
*8,730
*8,730
6.73 m
3
A
7.5 m
9.0 m
At Max. Reach Radius
B 7.5 m 6.0 m 4.5 m 3.0 m 1.5 m G. L. -1.5 m -3.0 m -4.5 m
13
kg kg kg kg kg kg kg kg kg
*20,320 *27,790 *21,730
*20,320 *27,790 *21,730
*18,360 *21,160 *22,130 *21,660 *19,830 *16,000
*18,360 20,680 20,050 19,980 *19,830 *16,000
*11,310 *13,200 *14,830 *15,780 *15,830 *14,730 *11,500
*11,310 *13,200 13,440 12,940 12,770 12,900 *11,500
*8,790 *8,970 *9,710 *10,690 *11,610 *12,190 *12,160 *10,930
*8,790 *8,970 *9,710 10,040 9,590 9,290 9,180 9,350
*8,090 *9,310 *9,730 *9,870
7,590 7,390 7,180 7,050
*5,840 *5,610 *5,630 *5,870 *6,350 *7,170 *8,570 *10,240 *10,070
*5,840 *5,610 *5,630 *5,870 *6,350 6,880 7,530 8,950 *10,070
7.86 m 8.68 m 9.18 m 9.41 m 9.40 m 9.14 m 8.61 m 7.75 m 6.43 m
SK480LC A
Standard Arm: 3.45 m Bucket: 1.9 m3 ISO heaped 1,510 kg Shoe: 600 mm 1.5 m 3.0 m 4.5 m 6.0 m
7.5 m
9.0 m
SK480LC-8
10.5 m
At Max. Reach Radius
B 7.5 m 6.0 m 4.5 m 3.0 m 1.5 m G. L. -1.5 m -3.0 m -4.5 m -6.0 m
kg kg kg kg kg kg kg kg kg kg
SK480LC A
*7,930 *7,930 *9,740 *9,740 *13,390 *13,390 *15,010 *15,010 *19,640 *19,640 *26,610 *26,610
*17,500 *20,650 *20,810 *22,070 *21,100 *18,970 *15,020
*17,500 17,770 17,050 16,870 16,990 17,380 *15,020
*12,400 *14,260 *15,480 *15,950 *15,610 *14,260 *11,120
*12,400 11,580 11,000 10,740 10,720 10,950 *11,120
Short Arm: 3.0 m Bucket: 2.1 m3 ISO heaped 1,560 kg Shoe: 600 mm 3.0 m 4.5 m 6.0 m
*8,750 *9,930 *11,050 *11,890 *12,280 *12,070 *10,890
*7,160 *7,350 *8,750 *7,870 8,780 *8,540 8,260 *9,200 7,880 *9,710 7,670 *9,900 7,650 *9,500 7,840
*7,160 7,060 6,800 6,480 *7,350 6,170 *7,950 5,940 5,820 5,850
7.5 m
*6,550 *6,550 *6,550 5,860 *6,750 5,220 4,880 *7,150 4,860 4,730 *7,820 4,720 *8,420 4,780 *8,870 5,100 *9,380 5,790 *9,900 7,180 *10,250 *10,250
9.16 m 9.87 m 10.31 m 10.52 m 10.51 m 10.28 m 9.81 m 9.07 m 7.98 m 6.35 m
At Max. Reach
9.0 m
Radius B 9.0 m 7.5 m 6.0 m 4.5 m 3.0 m 1.5 m G. L. -1.5 m -3.0 m -4.5 m -6.0 m
kg kg kg kg kg kg kg kg kg kg kg
SK480LC A
*12,410 *20,100 *24,550
*12,410 *20,100 *24,550
*18,790 *15,970 *17,860 *21,900 *20,570 *18,030 *13,310
*18,790 *15,970 17,020 16,980 17,190 17,660 *13,310
*11,060 *13,090 *14,790 *15,800 *16,030 *15,420 *13,690
*8,330 *9,290 *10,410 *11,430 *12,150 *12,390 *11,950 *10,240
*11,060 12,270 11,460 10,980 10,790 10,850 11,150
Long Arm: 4.9 m Bucket: 1.35 m3 ISO heaped 1,250 kg Shoe: 600 mm 1.5 m 3.0 m 4.5 m 6.0 m
*8,330 9,240 8,690 8,220 7,880 7,730 7,760 8,050
7.5 m
*7,850 *8,300 *8,910 *9,510 *9,920 *9,950
9.0 m
6,970 6,730 6,440 6,170 5,970 5,890
*7,930 *7,720 *7,630 *7,790 *8,170 *8,450 *8,790 *9,180 *9,570 *9,880 *9,660
10.5 m
*7,930 7,250 6,100 5,430 5,070 4,940 5,030 5,410 6,200 7,830 *9,660
7.79 m 8.88 m 9.61 m 10.06 m 10.28 m 10.27 m 10.03 m 9.55 m 8.79 m 7.65 m 5.93 m
At Max. Reach Radius
B 9.0 m 7.5 m 6.0 m 4.5 m 3.0 m 1.5 m G. L. -1.5 m -3.0 m -4.5 m -6.0 m -7.5 m
kg kg kg kg kg kg kg kg kg kg kg kg
SK480LC A
*9,110 *9,110 *3,640 *3,640 *8,730 *8,730 *6,960 *6,960 *11,260 *11,260 *10,550 *10,550 *15,020 *15,020 *14,680 *14,680 *20,000 *20,000 *19,780 *19,780 *26,960 *26,960
*17,110 *17,110 *12,070 *19,960 17,300 *13,890 *21,360 16,550 *15,050 *21,580 16,310 *15,490 *20,710 16,410 *15,130 *18,550 16,830 *13,730
12,050 11,140 10,570 10,310 10,300 10,550
*8,180 *9,520 *10,680 *11,520 *11,890 *11,650 *10,430
*8,180 8,460 7,900 7,510 7,310 7,290 7,500
*6,400 *7,190 *8,030 *8,780 *9,330 *9,540 *9,180
*6,400 6,640 6,230 5,880 5,620 5,490 5,520
*5,070 *5,770 *6,110 *6,570 *7,090 *7,550 *7,840 *7,790
*5,070 5,400 5,200 4,960 4,710 4,490 4,350 4,310
*20,380 *20,380 *14,390 *14,390 *10,450 *10,450
ME Arm: 2.4 m Bucket: 3.4 m3 ISO heaped 2,190 kg Shoe: 600 mm 3.0 m 4.5 m 6.0 m
7.5 m
*4,390 *4,200 *4,150 *4,210 *4,380 *4,670 *5,130 *5,820 *6,900 *7,980 *8,430
*4,390 *4,200 *4,150 4,020 3,750 3,630 3,640 3,800 4,170 4,860 6,200
9.92 m 10.80 m 11.40 m 11.79 m 11.97 m 11.96 m 11.76 m 11.35 m 10.72 m 9.82 m 8.55 m
*8,730
*8,730
6.73 m
At Max. Reach
9.0 m
Radius B 7.5 m 6.0 m 4.5 m 3.0 m 1.5 m G. L. -1.5 m -3.0 m -4.5 m
kg kg kg kg kg kg kg kg kg
*20,320 *27,790 *21,730
*20,320 *27,790 *21,730
*18,360 *21,160 *22,130 *21,660 *19,830 *16,000
*18,360 21,020 20,390 20,320 *19,830 *16,000
*11,310 *13,200 *14,830 *15,780 *15,830 *14,730 *11,500
*11,310 *13,200 13,670 13,170 12,990 13,130 *11,500
Notes:
1. Do not attempt to lift or hold any load that is greater than these lift capacities at their specified lift point radius and heights. Weight of all accessories must be deducted from the above lift capacities. 2. Lift capacities are based on machine standing on level, firm, and uniform ground. must make allowance for job conditions such as soft or uneven ground, out of level conditions, side loads, sudden stopping of loads, hazardous conditions, experience of personnel, etc. 3. Bucket lift hook defined as lift point.
*8,790 *8,970 *9,710 *10,690 *11,610 *12,190 *12,160 *10,930
*8,790 *8,970 *9,710 10,210 9,760 9,460 9,350 9,520
*8,090 *9,310 *9,730 *9,870
7,730 7,530 7,310 7,180
*5,840 *5,610 *5,630 *5,870 *6,350 *7,170 *8,570 *10,240 *10,070
*5,840 *5,610 *5,630 *5,870 *6,350 7,010 7,680 9,110 *10,070
7.86 m 8.68 m 9.18 m 9.41 m 9.40 m 9.14 m 8.61 m 7.75 m 6.43 m
4. The above lifting capacities are in compliance with ISO 10567. They do not exceed 87% of hydraulic lifting capacity or 75% of tipping load. Lifting capacities marked with an asterisk (*) are limited by hydraulic capacity rather than tipping load. 5. Operator should be fully acquainted with the Operator’s and Maintenance Instructions before operating this machine. Rules for safe operation of equipment should be adhered to at all times. 6. Lift capacities apply to only machine as originally manufactured and normally equipped by KOBELCO CONSTRUCTION MACHINERY CO., LTD.
14
Doc. No
Method Statement & Risk Assessment of Sheet Piling Works
Rev. No.
10-0115P025-MS-015
3
Date
15/02/2017
Page
24of 24
APPENDIX I ATTACHMENT: MILL CERTIFICATES & FACTORY PRODUCTION CERTIFICATES