変更 点 HENKATEN
What does Henkaten means?
変更 = Henkoo = Changing 点 = Tem = Point
What does Henkaten means? Henkaten is an expression,
formed by ing two Japanese words creating a third word with specific meaning.
What does Henkaten means? Henkaten therefore means changing point. Henkaten management is a methodology used to record and track changes in the process that may cause deviations, failures and problems, and may also affect the product or result of this process.
Process Definition According to ISO 9001 - 2008, the process is: An
activity or set of activities using resources, and managed in order to enable the transformation of inputs into outputs.
Examples of Processes Changing a flat tire;
Sharpen a pencil; Inject plastic part; Inspect a component;
Shopping.
Characteristics of a Henkaten A Henkaten occurs when a process undergoes for a modification, planned or sudden, temporary or permanent, of that was originally planned as the final process directly affecting one of variables of the process.
Characteristics of a Henkaten Planned changes Preventive Maintenance ; A new employee is starting on the organization under training; Change the provider of raw material Update a work instruction; Layout changes.
Characteristics of a Henkaten Sudden changes Corrective maintenance; An employee which is absent is replaced by colleague; Using a component under a deviation; A new activity is inserted into the process.
Characteristics of a Henkaten Temporary changes and permanent changes Usually a not planned change is temporary, a condition to work until the previous and
official condition can be restored, but in some cases, a temporary change can become permanent.
Characteristics of a Henkaten Thus a Henkaten will impact one or more process variables, namely the change will always occur in one or more than one of the
variables in the process. People, Machine, Method and or Materials.
MANPOWER
MATERIAL
METHOD
Sub-cause
Sub-cause
Sub-cause
PROBLEM
Sub-cause Sub-cause
MACHINE
MEASUREMENT / ENVIRONMENT
Characteristics of a Henkaten What about Measurement and Environment? Any changing in these two variables, will affect directly the another variable, for example a new instrument for measurement will be recorded in
Method and if there is a very cold day, it will affect directly the people, material or even the machine.
Why to manage and control changes? In every change inside a process there is a learning period, Hence which more the
process is executed, less time it takes and higher is its efficiency, until the process
becomes stable.
Why to manage and control changes? Known process / Stable INPUT
PROCESS
OUTPUT
INPUT
PROCESS
OUTPUT
INPUT
PROCESS
OUTPUT
?
?
INPUT
PROCESS
OUTPUT
New process / Unstable ?
?
?
?
Why to manage and control changes? Every time that a known process or a stable process, undergoes a changing it becomes once again a new process, or unstable, because is quite hard do predict accurately how that modification is going to affect the result of the process, this results will take time to evaluate and judge.
Henkaten Management This material was made thinking in a small organization for didactic purpose, how bigger is the organization also the Henkaten management should be divided accordingly to make easy for the station leader to manage without doing it because if organization politics or his boss has given the order, the station or substation leader must see the Henkaten management as a key tool of management and control or it will be useless, becoming just an ordinary task and a waste of time.
Henkaten Management
Man Machine Method Material
Henkaten Management
Man First activity is to create all the necessary documents, in case if they are not available in the organization, most of the documents are required by best practices and also by ISO standards, the management of Man Henkaten requires a lot of activities by the leadership, and is the most hard to be managed appropriately, because it includes a key point in the changing process management, due the reason is simple, Man will operate the Machine, transforming and handling the Material following a Method and getting information from it. So it is required a good management on that variable. Also because people are not the same (physicaly, behavioral, etc) It requires need for individual training for leveling the operational capacity.
Henkaten Management
Man For the management of Man Henkaten, are necessary the following documents: Board for Henkaten Management; Employees skill map; Workstation layout; Record sheet;
Manpower Management Employees skill map, is a document which must be updated EVERY TIME that a new task is added or planned for employee or for a new employee, this document, gives to the leadership the ability of fast judgement in case of member absence and the replacement strategy for absent positions in the work station.
EMPLOYEE SKILL MAP ACTVIVITY / NAME
ANDRZEJ
ARMAND
BORYS
CLEITON
ELKA
FRANCISKA
NIKOLAI
PATRYK
TEODOR
Activities / job positions
INJECTION LINE 01
PRESS LINE 01
MACHINING LINE 01
ASSEMBLE LINE 01
INJECTION LINE 02
PRESS LINE 02
MACHINING LINE 02
ASSEMBLE LINE 02
LEGEND
NO SKILL ON THE ACTIVITY
TRAINED IS PLANNED
CAN PERFORM THE ACTIVITY SUPERVISION IS REQUIRED
CAN PERFORM THE ACTIVITY NO SUPERVISION REQUIRED
TR
CAN TRAIN OTHER MEMBER ON THE ACTIVITY
Employee’s name and photos
Manpower Management
Manpower Management
Workstation Layout, is a simple diagram showing all the workstations on the shop floor, a scaled drawing of the production lines localization, machines, work stand, and if possible employee’s position on the line or at the machine.
Manpower Management PRESS
INJECTION 1
1
2
Employee’s photos
MACHINNING
ASSEMBLE
2
Employee’s photos should be placed by using magnets, making it easy to change positions when necessary.
1 1
2
2
WORKSTATION LAYOUT
Manpower Management
Record Sheet, is a sheet where the leader can make all the necessary s for keep the changing under control, plan the necessary activities and to make historical data from every changing in his area.
Manpower Management RECORDING SHEET OF MANPOWER CHANGING DATE
CHANGING
REASON
LOCATION
PLANNED OR SUDDEN
PERMANENT OR TEMPORARY
ITENS TO CHECK
HOW LONG
APPROVED
June 06th 2016
Elka is taking Armand position
Armand is absent due sickness
Injection Line 01
Sudden
Temporary
Only key itens from PIS first and last part of the batch
June 06th 2016
TEODOR
June 07th 2016
Nikolai is training with Borys
Nikolai was assigned for a new position
Press Line 01
Planned
Permanent
All PIS itens first and last part of the batch
Until August 07th 2016
TEODOR
Machining Line 01
Planned
Temporary
Only key itens from PIS first and last part of the batch
June 10th 2016
TEODOR
Assemble Line 01
Planned
Temporary
N/A
Until August 08th 2016
TEODOR
June 08th 2016 June 08th 2016
Cleiton is taking Andrzej Line must product during position the lunch time Patryk is trainning Franciszka position
Franciska is going to take vacations
This example sheet was created based on 5W2H, but it could and should modified according with the organization necessities, its culture and internal best practices
Henkaten Management
Machine First activity is to create all the necessary documents, in case if they are not available in the organization, most of the documents are required by best practices and also by ISO standards. Machine management if quite simple if comparing with manpower. This monitoring requires knowledge of the main wearing parts and their life.
Henkaten Management
Machine For the management of Machine Henkaten, are necessary the following documents:
Board for Henkaten Management; Preventive maintenance plan; Workstation layout; Record sheet;
Machine Management Preventive maintenance plan, is a document in which every maintenance programed in advanced for every machine on the shop floor is listed, and this document should contain at least the machine name, position, date for the maintenance and person in charge for the maintenance. It should be most clear that every maintenance, planned in advanced as well the sudden, is a machine Henkaten. Most important on this activity, maintenance department and manufacturing department must act together, but the Henkaten management must be of manufacturing department, because in this relationship, manufacturing department is a customer from maintenance department.
Machine Management PRESS
INJECTION 1
1
2
2
Machine’s position on the shop floor.
MACHINNING
ASSEMBLE
1 1
2
2
WORKSTATION LAYOUT
Machine Management
Record Sheet, is a sheet quite similar with the sheet used to control manpower Henkaten, there are although additional fields on that sheet: Part produced after changing; Quantity produced after changing;
Machine Management RECORDING SHEET OF MACHINE CHANGING PLANNED OR PERMANENT PN PRODUCED AFTER OR CHANGING SUDDEN TEMPORARY
QTY PRODUCED AFTER CHANGING
DATE
WHO
CHANGING
LOCATION
June 06th 2016
FRANCISKA
Die changing
Injection Line 01
Planned
Permanent
PART 12345-123
2000 SHOTS
June 07th 2016
ANDRZEJ
Changing the guide pin
Press Line 01
Sudden
Permanent
PART-12345-124
1000 PARTS
Holes position and size
APPROVED
June 08th 2016
TEODOR
Machining Line 01
Sudden
Temporary
PART-12345-125
10.000 PARTS / NEXT CHANGING COME BACK TO USE THE CORRECT OIL
Burrs and surface appearance
APPROVED
June 08th 2016
CLEITON
Assemble Line 01
Planned
Temporary
PART-12345-126
3000 PARTS
Weld cut check test in the first and last of the batch
APPROVED
Changing the cutting oil for a substitute, due missing of correct oil Changing of welding electrodes due the wore out before the expected time
ITENS TO CHECK
APPROVED
All PIS itens first and last APPROVED part of the batch
This example sheet was created based on 5W2H, but it could and should modified according with the organization necessities, its culture and internal best practices
Henkaten Management
Method First activity is to create the only 2 necessary documents, in case if they are not available in the organization, one of its of the documents is also requested by best practices and also by ISO standards. Method management is even more easy than Machine.
Henkaten Management
Method For the management of Method Henkaten, are necessary the following documents: Board for Henkaten Management; Record sheet; Correlation documents list;
Method Management Record Sheet, is exactly the same of Machine, but the contents of records will be different, once the changing in Method will be on documents, process parameters such as velocity, temperature or quantity. what is important to handle parameters as Method Henkaten, not machine, the reason of that is simple, machine modifications are done when mechanical modifications are performed.
Machine Management RECORDING SHEET OF METHOD CHANGING PLANNED OR PERMANENT PN PRODUCED AFTER OR CHANGING SUDDEN TEMPORARY
DATE
WHO
CHANGING
LOCATION
June 06th 2016
CLEITON
Increase of temperare of injection
Injection Line 1
Sudden
Temporary
June 07th 2016
ANDRZEJ
Modification of work instruction
Press Line 1
Planned
Permanent
QTY PRODUCED AFTER CHANGING
ITENS TO CHECK
APPROVED
12345-127
500 shots
All PIS itens first and last part of the batch
TEODOR
12345-128
1000 parts
All PIS itens first and last part of the batch
TEODOR
This example sheet was created based on 5W2H, but it could and should modified according with the organization necessities, its culture and internal best practices
Method Management Correlation document list, is a list required by QMS or the ISO standards, in this list there is a correlation between documents, the purpose of this list is to know or to what documents are necessary to modify when a new information is added or remove from one document.
Method Management DOCUMENTS CORRELATION LIST EXAMPLE DOCUMENT CHANGED / DOCUMENT TO CHECK
PFMEA
PFMEA PROCESS CONTROL PLAN WORK INSTRUCTION PIS
o o X
PROCESS CONTROL PLAN
WORK INSTRUCTION
o
o o
o X
PIS
o o o
X
MACHINE PARAMETERS SHEET
CHECK LIST OF MACHINE
SETUP INSTRUCTION
PACKING INSTRUCTION
X o
o
o o o X o
MACHINE PARAMETERS SHEET
CHECKLIST OF MACHINE SETUP INSTRUCTION PACKING INSTRUCTION COSTUMER DOCUMENTS
o X o
o X o
X X o
X o o
o X o
o X o
COSTUMER DOCUMENTS
The only reason of that list exists is to remind people all documents that one changing is applied, if the organization have another mechanism for this activity so it can be used.
Henkaten Management
Material First activity is to create the record sheet, because is the only document necessary, in case if they are not available in the organization, and this document is quite similar to all the other record sheets.
Material Management RECORDING SHEET OF METHOD CHANGING PLANNED OR PERMANENT PN PRODUCED AFTER OR CHANGING SUDDEN TEMPORARY
DATE
WHO
CHANGING
LOCATION
June 06th 2016
BORYS
Master Batch supplier changing
Injection Line 1
Sudden
Temporary
June 07th 2016
FRANCISKA
Thickness of coil
Press Line 1
Planned
Permanent
QTY PRODUCED AFTER CHANGING
ITENS TO CHECK
APPROVED
12345-129
100 shots
All visual itens of PIS 5 parts every 30 minutes
TEODOR
12345-130
1000 parts
All PIS itens first and last part of the batch
TEODOR
This example sheet was created based on 5W2H, but it could and should modified according with the organization necessities, its culture and internal best practices
Henkaten Management Visual aid The visual aid, it simple to apply any visual detection forms to help in fast identification of some information, this way you can also apply the selected color for each 4Ms, to all relevant documents and controls, thus creating a distinction and visualization fast each change that is occuring in the shop floor, this could be trigger to top management to get involved if necessary.
Henkaten Management
Man - Red Machine - Yellow Method – Green Material - Blue
Thanks for your attention!